Concrete

High-voltage (HV) cabin with a through-flow plinth: pilot project for climate-resilient electrical infrastructure

Texte & photos Lithobeton

Un socle surélevé et traversant a été conçu comme une solution durable et reproductible.
Un socle surélevé et traversant a été conçu comme une solution durable et reproductible.

A pilot project was recently completed in Afsnee, with the installation of Belgium’s first operational HV cabin featuring a through-flow plinth. The project is the result of a collaboration between Fluvius and Lithobeton, and offers a practical response to the growing challenges of building (prefabricated) structures in flood-prone areas.

Technical challenge

In practice, HV cabins are generally built on a solid concrete plinth. In areas exposed to flooding or the risk of water overflowing, however, this conventional approach can create a dangerous combination of water and electricity. A raised, through-flow plinth was designed as a durable, repeatable solution.

The new plinth has openings in its side walls, allowing water to flow in and out. The structure lets water pass through without putting the electrical components at risk. The solution combines the structural strength of reinforced concrete with greater climate resilience, without compromising the functional requirements of the high-voltage substation.

A pilot project was recently completed in Afsnee, with the installation of Belgium’s first operational HV cabin featuring a through-flow plinth.

Relevance to climate adaptation

The installation in Afsnee is the first application of this type of plinth in Belgium and can be seen as an important step towards climate-adapted electrical infrastructure. With extreme rainfall and local flooding expected to increase, it is becoming essential to adapt existing design principles where the application calls for it. The concept demonstrates that, with targeted modifications, precast concrete products can make a significant contribution to the safety and durability of utility infrastructure in a changing climate.

This project illustrates the value of practical collaboration between the client (Fluvius) and the manufacturer (Lithobeton). The exchange of expertise resulted in a technically feasible, repeatable solution that can be applied using current construction practices.

Broader applications across the sector

Although the Afsnee project was developed as a pilot, it opens up possibilities for wider application in other flood-prone regions. The through-flow plinth principle can be used not only for high-voltage substations, but also for other utility infrastructure where stability and water safety are critical. For the precast concrete sector, this represents an opportunity to drive further innovation in climate-resilient product development. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeNew ways of building
  • SubjectConcrete
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.