Scaffolded solutions to meet the building’s complexity

Texte Philippe Selke Photos Lauriane Genart pour Duchêne

La blancheur immaculée à la Santiago Calatrava est ici enrichie d’habillages en bois apportant une touche chaleureuse au « vaisseau » ferroviaire.
La blancheur immaculée à la Santiago Calatrava est ici enrichie d’habillages en bois apportant une touche chaleureuse au « vaisseau » ferroviaire.

At the end of December 2024, nearly 10 years behind the original schedule, Mons’s « gare Calatrava » was brought into service, echoing the station designed by the same Spanish architect in the Cité ardente. With the final cost multiplied by 12, the project evolved into an impressive intermodal footbridge, 165 m long, 33 m wide and 16 m high, linking the city centre and the Grands Prés district. Duchêne brought its expertise, versatility and flexibility to bear in completing a large part of the finishing works within a very short timeframe.

On this « pharaonic » project for SNCB, which was marked in particular by company bankruptcies, Duchêne came in at the final stage to complete the second-fix and finishing works in the car parks, plant rooms, sanitary facilities and offices, among other areas, as well as on the footbridge and its travel centre. Dependent on the completion of the shell-and-core works and the installation of specialist systems, the finishing works ran from September 2021 to December 2024, with several lengthy interruptions caused by delays attributable to other trades.

Even the car parks look as if they have come straight out of a Jules Verne novel.

Working at high speed

Patricio Borriero, Site Manager at Duchêne: « In addition to price, this public contract included other award criteria, including planning, as sufficient resources had to be available to meet the deadline after so many delays had already accumulated. To maintain an appropriate pace, I was supported by two site supervisors, with two more joining us during the final four months. At the peak of the project, we were supervising up to 40 workers employed by subcontractors. Our work covered the finishing of the two car parks, as well as the SNCB offices, which were not all part of the original project, before moving on to the most visible part, namely the footbridge and its travel centre. This involved completing all the interior cladding, in diamond board and, in some areas, wood. Various metalworking tasks for the signage on the platforms were also added to the scope. »

The footbridge is lined with 14 retail and service units.

High-wire work and a touch of wood

Finishing such a large triangular-section footbridge is obviously not as straightforward as completing the finishes in a rectangular building. The suspended ceiling to be installed was angled at 30 degrees, and working at height required a particularly sophisticated scaffolding set-up, all while other contractors were working alongside us. Cladding the ceilings of the 14 retail units lining the footbridge called for a huge scaffolding operation, and rope-access technicians even had to be brought in to reach areas beyond the reach of the scaffolding.

The immaculate white finish characteristic of Santiago Calatrava’s Belgian stations is enhanced here with timber cladding made by Duchêne’s joinery department, which was called in to add a warm touch to the railway « vessel » at very short notice. Romain Campion, Site Manager at Duchêne’s Joinery Department: « 1000 linear metres of plywood shells cladding the vertical members of the triangles were made to three different designs and then re-laminated in our workshop. The laminated pieces and panels (850 m2) for cladding the 115 rooflights were first produced as a mock-up. Finally, following a last-minute request from the architect, 46 triangles in the suspended ceilings were clad in wood. Given the quantities involved, this was a significant challenge for the workshop, and installation was also challenging, as we had to work with both access platforms and rope-access technicians. » Duchêne’s teams managed to complete all this in 3 months for the shells and rooflights, followed by a further 20 days to install the wooden triangles, with 6 workers in August 2024. As an aside, these triangles are remnants of a much more extensively timber-clad design for the footbridge, which was cut back due to budget restrictions towards the end of the project.

The Mons station project also includes offices and meeting rooms for SNCB staff.

On this project, as on others, Duchêne adapted to changing circumstances with flexibility and versatility, helping to meet the final delivery deadlines. The capital of Hainaut can take pride in a station worthy of a major city, probably the last of its kind at a time when the rail network manager is prioritising restraint.  

Technical details

Client SNCB
Architect Santiago Calatrava
Shell-and-core contractors Cordioli (bankrupt), Pirson then BPC Group, CIT Blaton
Finishing contractor Duchêne

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectHainaut