La nouvelle salle d’exposition de Cuisines Dovy à Zaventem illustre la manière dont un projet commercial peut conjuguer exigences architecturales, contraintes logistiques et efficacité constructive.
La nouvelle salle d’exposition de Cuisines Dovy à Zaventem illustre la manière dont un projet commercial peut conjuguer exigences architecturales, contraintes logistiques et efficacité constructive.

The new Cuisines Dovy showroom in Zaventem shows how a commercial project can combine architectural requirements, logistical constraints and construction efficiency. Built by Mahieu Construct, the building stands out for both its layout and its location close to the national airport. With a full basement, a largely prefabricated structure and complex geometry, the project required particularly rigorous planning.

Unlike several other showrooms built for the brand across the country, the Zaventem project has a basement level with parking, which had a significant impact on the construction methods. “This showroom is more complex than the previous ones, particularly because of the underground car park and its location,” explains Lowie Vandewalle, project manager at Mahieu Construct.

Work began at the end of February 2025 with excavation and the installation of Berlin-type retaining walls. Constructing the in-situ concrete basement was a major phase of the project, before work on the superstructure began in spring.

Completed in October 2025, the building provides space to display around thirty kitchens across two above-ground floors, plus an intermediate level approximately 1.80 metres above floor level. This mezzanine plays an important role in the visitor route, creating a natural transition between the different showroom areas. The programme is completed by just a few staff facilities.

The Zaventem project has a basement level with parking, which had a significant impact on the construction methods.

Prefabrication as a driver of efficiency

The structure combines a steel frame, precast concrete panels, prestressed hollow-core slabs, steel deck units and sandwich panels. With the exception of the hollow-core slabs, the structural elements come directly from the group’s production facilities.

This approach offers several advantages. It helps optimise manufacturing times, limit on-site uncertainties and, above all, respond more quickly to any changes to the project. “Because the elements are manufactured in-house, we can respond quickly and remain very flexible,” says Lowie Vandewalle.

Far from being a conventional rectangular volume, the building features numerous angles, recesses and cantilevers.

This layout made it impossible to use standard elements throughout. Formwork and in-situ concrete pours were therefore needed to meet the project’s volumetric requirements.

Far from being a conventional rectangular volume, the building features numerous angles, recesses and cantilevers.

A logistical and administrative challenge

The site’s proximity to Brussels National Airport was one of the project’s main challenges. A lack of available space meant a tower crane had to be used, whereas the company would usually opt for mobile telescopic cranes.

Any operation requiring tall equipment, such as concrete pumps or the tower crane, had to be authorised in advance by the airport authorities. Several delivery phases also required temporary road closures.

Managing the excavated soil was another major challenge. The large volumes generated by the earthworks had to be removed under particularly strict regulatory requirements.

The structure combines a steel frame, precast concrete panels, prestressed hollow-core slabs, steel deck units and sandwich panels.

Coordination and in-house expertise

This project clearly demonstrates the added value a company such as Mahieu Construct brings. The design work was carried out using 3D modelling to anticipate construction details and facilitate coordination between teams. Drafting staff, site planners, team leaders and project managers worked together throughout the project.

“Our strength lies in our teams’ experience and in the fact that most of the components are produced in-house,” says Lowie Vandewalle.

Completed in autumn after 8 months of work, the Cuisines Dovy project in Zaventem demonstrates how prefabrication, combined with meticulous planning, can effectively meet particularly demanding technical and logistical constraints.

Project details

  • Client: Cuisines Dovy
  • Architect: Ypsilon Architecten
  • Main contractor: Mahieu Construct

Een zakelijke vraag aan Mahieu Construct? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeLow-carbon transport and mobility
  • SubjectConstruction
  • CompanyMahieu Construct
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.