Preparing the ground for the new inpatient tower
Texte Philippe Selke Photos Franki Foundations

Before the future inpatient tower at Cliniques universitaires Saint-Luc can rise above ground, major work must be carried out… below ground. As part of the site’s redevelopment, Franki Foundations is working in several areas using a range of retaining and specialist foundation techniques. The particular challenge on this project is that the work is taking place at the heart of a hospital that remains fully operational.
A series of retaining structures
The HospitaCité project includes the construction of a new inpatient tower and the renovation of the existing medical and technical base.
As part of the enabling works entrusted to Jacques Delens, Franki Foundations is responsible for a series of retaining structures to prepare for the future excavation. “The idea is to prepare the excavation for the major project that will follow, the construction of the new hospital,” explains Etienne Delheusy, Project Manager at Franki Foundations.
Work began in November 2025. A first secant pile wall created a new entrance to the existing car park, as the former entrance lay within the footprint of the future works. A soil-nailed wall was then built to replace a prefabricated L-shaped retaining wall. This alternative reduced the need for sloped excavation and avoided the felling of several trees.

Working around an operational hospital
Further work followed: two shored excavations six to seven metres deep in an existing basement, a soil-nailed wall along avenue Hippocrate, and underpinning of existing buildings and structures.
The challenge is not purely technical. Much of the hospital remains operational in the immediate vicinity, which directly affects construction methods. “Where we could have built a Berlin-type wall, we can’t do so because the operating theatres are highly sensitive to vibration,” explains Etienne Delheusy.
The work in the basement called for additional precautions. The work areas are located close to loading bays used to supply the hospital. The excavations were therefore kept under negative pressure to prevent dust from spreading. Some concreting operations also had to be scheduled outside operating hours, with carbon monoxide levels monitored.

Diaphragm walls extending down to the clay
The largest phase concerns an area measuring approximately 50 metres by 170 metres. Diaphragm walls are to be built here to allow excavation of the future basements. They will extend down to the clay layer, enabling the groundwater table to be lowered during excavation.
The operation also poses a logistical challenge. “It’s not easy to bring 7,000 to 8,000 m³ of concrete and 20-metre-long reinforcement cages to this location,” says the Project Manager. The roughly 10-metre difference in level between avenue Hippocrate and avenue Mounier further complicates the planning. The working platforms must be wide and stable enough to accommodate the machinery, and must be prepared in stages to ensure the work can proceed continuously.

More stringent design requirements
These constraints are compounded by structural requirements specific to the future hospital building. While many structures are usually assigned consequence class CC2, the structures in question here are designed to CC3. Additional safety factors must therefore be applied to the secant piles and diaphragm walls, in accordance with the specifications and the requirements of the engineering consultancy Sweco and the inspection body SECO.
Some underpinning work also reaches a depth of 15 metres. It must extend the foundations of the existing buildings to the level required for the future excavation. “This means excavating down to a depth of 15 metres by hand,” explains Etienne Delheusy.
Franki Foundations’ work is expected to continue until after summer 2027. This underground phase will largely be invisible in the long term, but is essential before the new inpatient tower can take shape.