Managing budget and schedule while maintaining quality
Texte Philippe Selke Photos ACH Build

At the start of the 2024 academic year, agronomy bachelor’s students were delighted to move into the brand-new building of the Haute Ecole de la Province de Namur in Ciney. With 8 classrooms, a 228-seat lecture theatre, laboratories, a library, a cafeteria, administrative offices, … spread over three floors and with a total floor area of 3400 m2, the new complex is a huge step up from the previous premises, which were 35 years old. The Province entrusted the works to the family-run general contractor ACH Construct (Les Bons Villers).

ACH Construct traces its origins back to a small joinery business … in 1884. Today, the company, now a general contractor, has many strings to its bow: in addition to renovation and restoration (D24), it is known for building swimming pools, and has expanded its expertise to include their operation, as well as social housing, care homes and, of course, schools, with an extensive portfolio ranging from nurseries to universities, whether under public contracts or on a design & build basis.
Schedule met
Work began in March 2022 and was due to finish in June 2024. The public contract was completed at pace, despite a slight delay caused by soaring material prices. Eddy Verdin, now commercial director at ACH Construct, explains: “For the long spans in the lecture theatre, we had ordered glued laminated timber beams from Austria. Following the price surge, we had to renegotiate the contract to release the beams, which were held up at the Austrian border. This still cost us a month. Apart from that, everything went to plan and we were able to deliver on time.” The external works were covered by a separate contract and were delivered in September 2024.

Optimising without compromising
The structural work is mainly in concrete, with precast elements used to optimise construction time. “This public contract did not allow us to propose alternatives. However, we were able to switch certain elements to off-site prefabrication rather than casting them in situ. A project that takes longer costs more in fixed overheads, such as cranes and scaffolding. That is the main reason we favour prefabrication, so we can minimise delays.”
Another way to optimise costs is to take care with the structural work so that it can also serve as the finish. ACH Build has its own steel fixers, formworkers, concreters, bricklayers, … who deliver high-quality work in their respective trades while also turning their hand to other tasks when needed. This avoids having to subcontract every minor work package. Eddy Verdin says: “Our teams built attractive concrete blockwork that was left exposed, eliminating the need for painting and saving the client money. The glued laminated timber beams used for the long spans offer the same advantage: they are finished in themselves.”

Juggling multiple projects
With the work completed to expectations and the original deadlines met, ACH Construct has once again demonstrated its ability to manage projects while maintaining construction quality and meeting the requirements of public contracts. Elsewhere in Wallonia, the family-run company is about to start work on lecture theatres with a total capacity of 2000 for the University of Mons, following a competition it won last year. In Gembloux, it has just laid the foundation stone for the future community centre. These are projects well worth following, among many others…

Technical specifications
Client Province of Namur: Property Heritage Technical Department
Architect AW architectes
General contractor ACH Construct