Another project running smoothly for LETEC
Texte Philippe Selke Photos AM Duchêne – Galère

At the Mécalys industrial park in Andenne, work on LETEC’s future maintenance centre is nearing completion, 70 working days ahead of the imposed schedule. Carried out by contractors Duchêne and Galère in a temporary joint venture, with Bureau d’Architecture Greisch and Lemaire Ingénieurs as project designers, the project nevertheless presented constraints, notably relating to the ground, available space and coordination of external works. A challenge successfully met!
Work actually began in October 2024. The project aims to replace the Seilles workshop, which is no longer fit for purpose. It represents an investment of almost €33 million and will accommodate around a hundred drivers, mechanics and administrative staff.
The workshop is the beating heart of the project, with inspection pits for working beneath vehicles, walkways for working at height, a paint booth and various pieces of equipment for maintenance and roadworthiness testing. A bus wash, social spaces and offices complete the facilities. The site is also designed to accommodate a fleet of electric buses and has a large rooftop photovoltaic installation.
Connected to the main building by a footbridge, a car park for staff overlooks the area reserved for bus parking.
Duchêne and Galère: an integrated approach
Unlike the Mobi’Park project in Tilleur, which was carried out by the same companies (see the previous issue of Construire la Wallonie), where the roles were divided between building construction and external works, Duchêne and Galère worked here as an integrated team.
The timeframe was a decisive factor from the outset. The aim of the temporary joint venture was to optimise the schedule to just 380 days. “This challenge helped us win the contract while also keeping costs down: the faster you complete a project, the less it costs,” explains Giovanni Montagnino, project manager at Duchêne. The works are therefore scheduled for completion in September 2026.

Working with waterlogged ground
However, progress at the start was slowed by particularly wet weather. The project called for minimising the removal of soil by reusing it after lime treatment on site. The weather conditions had other ideas. “If the ground is saturated with water, the lime does not react as intended and the required load-bearing capacity is not achieved,” explains Giovanni Montagnino.
Some of the soil therefore had to be removed and replaced with soil that had been treated with lime in advance. This adjustment was necessary to continue the work under the required conditions.
Many contractors on a compact site
The project was also complex because work by a large number of different partners had to be coordinated on a relatively compact site. These included HD Systems (cladding and roofing), Reno-tech (waterproofing), SEPPI (electrical works), Dethier Group (sanitary & HVAC), Ets E. Ronveaux (concrete structure), CMIX (concrete supply), Bemelmans (steel structure), Solalux (polished concrete slabs), IFC, International Fire Control (fire safety), …
All in all, the project was completed smoothly. The project manager is keen to highlight the quality of the collaboration with the client and project designers.
The result? A modern site designed to support the energy transition, embodying OTW’s commitment to combining environmental performance, technological innovation and quality of working life.

PROJECT DETAILS
Client: Opérateur de Transport de Wallonie (OTW, LETEC)
Project designers:
Bureau d’Architecture Greisch (BAG)
& Lemaire ingénieurs
Contractors: SM Duchêne, Galère