Rail engineering specialist completes prestigious projects in Flanders and Wallonia
Texte Wouter Polspoel | Photos De Witte-Vandecaveye

After successfully completing two prestigious projects for Infrabel, De Witte-Vandecaveye, a specialist in electrical works and railway technology, among other fields, was able to start the construction holidays with a great sense of satisfaction. Along railway line 50A, the Wingen-based company built a service walkway beside a 1.75 km stretch between Ghent and Wetteren. The embankments were reinforced and retaining walls installed along 1.25 km. In Visé, it then renewed the sleepers and rails on one of the two railway tracks on a railway bridge over the Albert Canal.

The project along railway line 50A, from Brussels to Ostend, involved several phases. “In the first phase, we removed the signalling, power supply and fibre-optic cables from the old cable ducts, which we then removed along an 800-metre stretch. We also reinforced the embankment with L-shaped retaining walls wherever necessary, over a total length of 450 metres. Finally, we built a new service walkway,” explain project managers Matthias Broucke and Nico Desmet. “This first phase took place in November and December 2022. We worked every night for around ten weeks, as well as over two full weekends. Train services through the work zone were suspended throughout the works.”
Just before the construction holidays, De Witte-Vandecaveye completed the second phase of the works. “This involved a 950-metre stretch, where we had to reinforce 600 metres of embankment with L-shaped retaining walls. The second phase lasted about as long as the first, with the same working pattern.”
During the second phase, a slightly different approach saved a great deal of time. “At the end of last year, we used rail wagons to remove concrete waste from the demolition of an 800-metre cable duct, storing it in an area beside the railway and then taking it away by works train at the weekend. The waste was transferred to lorries, which then took it to a processing plant,” the project managers explained. “We made sure the works train was available straight away during the demolition work at night, and unloaded it during the day. This working method saved a great deal of time. At the end of this year and in 2024, De Witte-Vandecaveye will renew another two kilometres of railway line 50A in the same way.”

A railway bridge with multiple challenges
“The railway bridge, which is 420 metres long overall, forms part of a freight line. We renewed the sleepers and rails on one of its two tracks,” explains project manager Jonas Baecke, speaking about the project in Visé. The project also included sandblasting and painting the bridge. “For a railway line at ground level, ballast is normally used. On many railway bridges in Belgium, rails can be laid in the same way, using a container beneath the bridge filled with ballast. The situation in Visé was different, however: the sleepers were fixed directly to the steel structure, which made the work fairly difficult. The steel pillars between the bridge’s two tracks presented another challenge. As a result, we could not isolate the track from the adjacent one as we normally do, nor could we use the adjacent track to bring in materials. Trains therefore continued to run on that track.”
The solution was to build panels measuring 6 metres long and 2.5 metres wide, fitted with wooden sleepers and two rails. Together, these formed a short track section on which the rail-mounted crane could travel. “The panels were made in our workshop in Wingene and then transported to Visé,” explains Jonas Baecke. “After removing the old rails and sleepers, we laid the panels one by one on the bridge. This created a track from which we could work. Then, working backwards from the narrow-gauge track, the rail clamp removed the short rails panel by panel. We then slid the new rails, one section was 300 m long, onto the new sleepers, until we had a new 420 m-long railway track.”
“The project was unusual for other reasons too. Our staff stayed in a hotel in Verviers for the duration of the work, so they did not have to drive 2.5 hours each day to return to West Flanders. A subcontractor installed nets beneath the bridge to protect boats from falling tools, and our workers had to wear climbing harnesses at all times because they were working at a height of 30 metres.”
Work in Visé was completed in mid-June and ultimately lasted 10 weeks, spread between autumn 2022 and mid-June 2023. Dismantling took two weeks, sandblasting and painting the bridge took five weeks, work not carried out by De Witte-Vandecaveye, and laying the new track took three weeks.

Thinking outside the box
Asked how they would describe De Witte-Vandecaveye’s added value on projects like these, Broucke, Desmet and Baecke all reply in unison: “With our own design office, our experience in signalling, railway works and construction, and our extensive fleet of machinery, we can do everything ourselves on projects like these and do not depend on external parties. We also think outside the box, as demonstrated by the panel system we designed for the project in Visé.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectRailway technology