An exemplary construction project championing sustainability
Texte Philippe Selke Photos Philippe Piraux & Denis Closon

In Jemappes, the Forem’s new training centre dedicated to ecotechnologies and new materials was handed over in spring 2026, after around a year and a half of work. For Wust, which worked in a temporary joint venture with Structure Wood, this project covering around 6000 m² notably required construction methods to be adapted to a predominantly timber structure and to the DNSH environmental requirements linked to funding from the European Union’s Recovery and Resilience Facility.
The new centre is organised around a workshop area (4500 m2) and an office block (1500 m2). Six large workshops surround central classrooms overlooking the practical work areas. The office block houses offices, training rooms, an auditorium, a canteen and toilets. A substantial expanded-metal structure acts as a sunshade. The workshops’ pitched zinc roof accommodates around 900 photovoltaic panels, while the office block’s flat roof is green. The buildings operate without fossil fuels.

DNSH from the very first groundworks
The project is located on the former industrial sites of the Verrerie and Laminoirs de Jemappes, previously remediated by SPAQUE. Wust took over a backfilled platform with insufficient bearing capacity to support the piling rig. DNSH (Do No Significant Harm) requirements influenced the organisation of the work from this initial phase. Rather than remove the unstable soil and bring in new materials, the company chose to lime-stabilise the existing platform. “We had to limit transport, material deliveries to the site and removal of materials,” explains Frédéric Dupont, project manager at Wust. Around 300 piles were then installed to reach load-bearing ground, at a depth of around ten metres.
Recycled stone aggregates were also used, and the concrete for the foundation pads and bases came from a plant close to the site.
Timber and concrete
Assembly of the timber structure began in spring 2025. It includes glulam columns and beams, CLT floors and timber-frame façades insulated with wood fibre. However, the project is not built entirely from timber: the central core containing the lift and stairwell, as well as the auditorium, were constructed using exposed-concrete walls. The main staircase in the collaborative space is made from prefabricated exposed-concrete elements.
This combination of construction systems made thorough preparation all the more important. “Everything has to be planned perfectly in advance: the connections, openings and interfaces with the concrete or steel structures. When the timber frame arrives on site, it really is just a matter of assembly,” says Frédéric Dupont. Wust therefore had to coordinate its structural works closely with the rapid pace of timber-structure installation.

Reclaimed bricks
Another technical challenge was cladding the office block and the workshop’s side façades with 1500 m² of reclaimed bricks. Installing them on a timber frame resulted in different movement from that seen with a concrete structure. Specific studies and local reinforcements, particularly at the parapets, helped control these movements and prevent cracking in the cladding.
Work began in late 2024, and the project was handed over at the end of May 2026, with the centre due to open in August. The project manager highlights the quality of collaboration between the various parties: “We worked constructively with the architects at ABR, the engineering consultancy B Solutions, the client and our partner Structure Wood, and it worked well. The client is satisfied. This was a first for me, but I was able to rely on my colleague Antonino Cianchino, an experienced site manager who had already successfully delivered timber-structure projects.”