Restoring a centuries-old roof structure: a question of balance and passing on skills
Texte Philippe Selke Photos Charpente & Construction Bois

Beneath the roofs of Mons City Hall and its ancillary buildings are timber roof structures, some dating back to the late 16th or early 17th century. Since December 2023, Charpente & Construction Bois (CCBois) has been working on these structures as a subcontractor to main contractor Galère. Assessing the existing structure, installing temporary supports, splicing in new timber, replacing components and using traditional joints are all part of a project guided by the preservation of historic material.
CCBois’s work is being carried out over an extended period in three phases. The first began in December 2023 and covered, among other areas, the Saint-Georges chapel, the Toison d’Or, City Hall itself and its belfry. The teams were on site for four to five months.
A second phase followed in 2025, at the rear of City Hall, including the Salon Boisé. Finally, since July 2026, CCBois has been working on a third phase covering the rear buildings. This is due to continue until the end of the year.

The specifications meet the reality of the building
Several years can pass between drawing up the specifications, submitting a tender and carrying out the work. In the meantime, the condition of the timber continues to change.
A fresh on-site assessment is therefore essential. First, the structures are cleaned so that any deterioration becomes visible, and then they are surveyed. This makes it possible to compare three realities: what the specifications call for, what the roof structure actually reveals and what technical and budgetary constraints allow.
“It is not accurate to say that restoring a roof structure means rebuilding it in its entirety,” stresses Bruno Bodeveix. Some old structures remain largely sound despite their age. Restoration is therefore a matter of determining precisely how far to intervene.

Water, timber’s biggest enemy
At Mons, moisture is one of the main causes of deterioration. An ageing roof covering, a defective slate or a leaking gutter is enough to cause water ingress, which gradually damages the roof timbers over the years. Components built into the masonry are particularly vulnerable: their ends absorb moisture from the walls.
The same applies to wall plates, the horizontal members laid flat on the masonry at the foot of the roof slope, which support the rafters. Close to gutters and poorly ventilated, they can be exposed to moisture for prolonged periods. Depending on their condition, they are repaired or replaced. Rafters, which support the battens to which the slates are fixed, are more often replaced entirely.
The fixings are also renewed: CCBois carries out a comprehensive mechanical fixing operation and replaces the wooden pegs where necessary.

Surgical interventions
Preserving as much of the existing material as possible means working locally. “We work like a dentist, making splices either with timber or with resin,” explains Bruno Bodeveix.
Traditional joints are preferred wherever the configuration allows. But restoring a roof structure in situ is fundamentally different from rebuilding it in a workshop: since dismantling the whole structure is not an option, the carpenter has to adapt the joint to what remains.
The full extent of deterioration sometimes only becomes clear during the work. A seemingly limited area can extend to 2.5 to 3 metres once the decayed timber has been gradually removed. The question then is whether to continue the splice, using epoxy resin in particular, or replace the component entirely.
These discoveries are discussed with the design team and the heritage authorities. CCBois provides its technical assessment, but the final decision is made collectively, taking account of heritage conservation, stability and budget.
The belfry under strain
Among the work carried out, the belfry intervention stands out for its complexity. This structure was added in the early 18th century to house a large bell. Its weight contributed to the distortion of some parts of the roof structure, which had not originally been designed to bear these loads. A steel structure had already been installed during earlier work to relieve the load on the timber structure.
However, damage remained to the trusses and other load-bearing components. CCBois therefore carried out repairs, adaptations and localised replacements.
The geometry of the belfry made the work even more challenging. Very tall and slender, the structure leaves carpenters little room to work. Carrying out work on components that provide bracing or help transfer loads required the whole structure to be progressively secured with temporary supports and tensioning. “The more you intervene, the less working space you have. That’s the challenge,” says Thomas Varin, Heritage Manager at CCBois.
The belfry could have been completely dismantled, but that option was ultimately rejected. Restoration cannot be considered in isolation: taking down such a structure would have affected other work packages, particularly the roof covering. Carrying out the work on site was therefore the best option for the project as a whole.

Dozens of m3 of oak to be transported into the roof space
The structural challenges are compounded by the difficulty of handling materials. The amount of timber required for the various interventions runs to several dozen cubic metres. Galère provided the perimeter scaffolding and lifting equipment needed to raise the heavy materials.
From there, the work becomes more hands-on. Components have to be moved through the roof space on small wheeled trolleys, then hoisted and positioned using chain blocks. Teams usually comprise four to six people.
Preparation takes a considerable amount of time. Before cutting through an existing component, the team must work out how the loads will be transferred, shore up the structure, secure the area and plan how to move the new component into place. “We spend almost as much time preparing the site as we do making the timber component itself,” says Thomas Varin.

A third phase with a different focus
Since July 2026, work has focused on other buildings at the rear of the complex. The layout is different here: a succession of roofs, dormer windows, gutters and numerous junctions creates a host of individual challenges. The carpenters are working in particular on hips and on the junctions between different roof sections.
The work is due to continue until the end of the year, with one further constraint specific to Mons city centre: the site must occasionally close during events held nearby. This is a known constraint and has been built into the schedule.

Building for the future by passing on skills
The project also provides fertile ground for passing on skills. Assessing an old structure, installing temporary supports, selecting timber, cutting joints, working safely and adapting joints all expose young carpenters to situations rarely encountered in new-build construction. “We pass our knowledge on to the younger generation,” says Bruno Bodeveix.
This passing on of skills ultimately reflects the very logic of restoration: extending the life of what is already there rather than replacing it, by working precisely on what centuries of history, alterations and exposure to the elements have left behind.