Two complex renovations involving partial demolition and reconstruction

Texte Philippe Selke Photos eloy

A Flémalle, eloy a déconstruit avec précaution plusieurs volumes spécifiques afin d’uniformiser la surface.
A Flémalle, eloy a déconstruit avec précaution plusieurs volumes spécifiques afin d’uniformiser la surface.

What do Engie’s technical and administrative headquarters at the combined-cycle gas turbine (CCGT) power station in Flémalle and the new Espace Santé Meyerbeer in Spa have in common? Both are the result of meticulous renovation work by eloy’s teams, who drew on their multidisciplinary expertise to demolish part of the existing structure and then rebuild it to meet current standards.

Of the 19th-century former military stables, only three heritage façades have been retained.
A contemporary extension, hidden from view from the street, increases the building’s depth and usable floor area.

An electrifying renovation at Les Awirs

On the site of a former coal-fired power station, Engie built a gas-fired power station. eloy contributed to this major project by renovating the site’s only retained building.

Adrien Mairesse, site manager: “From March 2024 to November 2025, eloy delivered the technical and administrative headquarters for the new power station, with a ground-floor area of around 4,500 m². It houses offices, changing rooms, workshops, stores, a canteen, reception and sanitary facilities, as well as the control room.”

After strip-out, eloy removed specific sections, including a single-storey volume and a two-storey rear block, to create a uniform floor area. This demolition was carried out carefully to preserve the structure that was to remain, while materials were recovered and taken off site for reuse or recycling. The load-bearing structures were then strengthened, openings were formed and two canopies were built.

Among the challenges on site, Adrien Mairesse notes that conventional cranes could not be used because the work was being carried out beneath an existing roof. As a result, lightweight lifting equipment was used, including a Manitou, pallet trucks and small material hoists, while concrete was pumped through openings. The presence of other contractors working at the power station also meant that a dedicated work zone had to be cordoned off to minimise interaction and risk and ensure safe working conditions. Given the complexity, eloy used its own teams for demolition and drainage, subcontracting the structural work, electrical work and HVAC/plumbing.

The load-bearing structures were then strengthened, openings were formed and two canopies were built.

In Spa, monumental stables become a medical centre

The new premises of the Meyerbeer medical centre in Spa were inaugurated in February 2025, after 18 months of work. More modern and spacious, they are now housed in a former 19th-century military stable, of which only three heritage façades have been retained. Built from the rear of the site, the renovated building has three storeys and technical loft space. A contemporary extension, hidden from view from the street, increases the building’s depth and usable floor area.

Nicolas Haulet, site manager at eloy: “The façades to be retained were shored up using triangular structures, ballasted at the base and anchored to the façade with beams and threaded rods to ensure stability during the works. The new load-bearing structure was then erected in stages, before the façade was attached to it. It now serves simply as cladding, with no structural function.”

An unmapped culvert running through the building to connect avenue Reine Astrid with the Wayai stream required extensive surveys and changes to the foundations. Site access was restricted, with limited working space around the building, and close coordination with the police was needed to reach the rear via their facilities.

Drawing on its multidisciplinary expertise, eloy deployed its own teams for demolition, structural work, formwork, concrete and masonry.

Like the project for Engie at Les Awirs, this scheme demonstrates eloy’s versatility and its ability to adapt to the site’s technical and logistical constraints. As the future of construction increasingly lies in smart renovation, eloy is well placed to give Wallonia’s buildings a new lease of life. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings