The new jewel of the “Toboggan of the Ardennes”

« D’habitude, il y a un terrain plat, voir des parkings alentours, qui facilitent la construction. Ici, nous avons dû réaliser des plateformes pour y installer les grues indispensables pour utiliser du préfabriqué. »
« D’habitude, il y a un terrain plat, voir des parkings alentours, qui facilitent la construction. Ici, nous avons dû réaliser des plateformes pour y installer les grues indispensables pour utiliser du préfabriqué. »

General contractor Wust is active on all fronts, in both Belgium and Luxembourg. So when the world’s most beautiful circuit gets a facelift, the company, based in Thimister-Clermont, rolls up its sleeves to take on a major challenge.

Track renovation, bringing it up to standard to once again host motorcycle races, and the construction of a new grandstand: this was the overall contract to give the world-famous Spa-Francorchamps circuit a new lease of life. “Wust joined forces with Bodarwé on the track and with Serbi on the grandstand,” Kevin Goffinet, site manager, tells us on behalf of the consortium. 

A grandstand with 4,555 seats.

“Construction of the grandstand took place over the winter. It is a large structure made almost entirely from prefabricated elements. It has three levels. There are, of course, the stands, with a total of nearly 4,555 seats. There is also 1,800 ​m² of ‘hospitality suite’ space. The suites are fully insulated against heat and noise, so guests can hold a conversation without being disturbed by the sound of the cars. Spectators who want to enjoy the race can head out onto a large terrace of nearly 600 ​m² overlooking the Raidillon corner. Finally, level -2 houses nearly 1,000 ​m² of technical space. That is a lot of floor space to build in just 5 months. The suites are finished with kitchens and all the facilities needed for hospitality,” explains Kevin Goffinet.

“Spectators who want to enjoy the race can head out onto a large terrace of nearly 600 ​m² overlooking the Raidillon corner.”

Dizzying figures

The figures are dizzying: the grandstand is 125 metres long and 23 ​metres wide, with a total floor area of 2,875 ​m². It also includes 26 sawtooth beams, a 250-tonne assembly of 14 welded sections and 1 km of guardrails. All of this had to be installed in 5 months.

And 5 months is a very short timeframe in which to deliver a project of this scale, particularly at a time of year that is far from ideal for this type of work: “It was a real challenge to keep the teams and workers motivated, as they were working through the winter. We had to build the grandstand between 16/11 and 15/03, when the circuit is closed. We had cold weather, rain and even snow. The winter was kind to us, all things considered. At times, we even worked through the night,” says Kevin Goffinet.

Fortunately, the contractor had a few extra days to finish the hospitality suites. The grandstand had to be ready for the WEC, the 6 Hours of Spa-Francorchamps. “We finished the work on time, to the day. The Circuit was pleased with our work, and that is what matters most,” says Kevin Goffinet.

The grandstand has three levels: hospitality suites, hospitality facilities and seating.

Prefabrication was essential

As well as the very tight deadline and challenging weather conditions, the workers also had to contend with the particularities of the site. “We had to overcome the challenges inherent to the circuit. Bringing materials onto the site was difficult, as was installing cranes and access platforms. Everything had to be carefully planned and adapted to make the grandstand possible.
Normally, there is flat ground, or even car parks nearby, to make construction easier. Here, we had to build platforms for the cranes needed to handle the prefabricated elements,” explains Kevin Goffinet.

“In fact, without prefabrication, we would never have met the deadline. It was included in the original contract. And when you see the grandstand, this jewel in such a stunning circuit and setting, everyone who took part in the project can feel proud. Everyone made compromises and pulled together. Millions of television viewers got to see this project, thanks to everyone involved. We can be proud,” concludes Kevin Goffinet.   

Question about this story? Ask your question

Who worked on it

  1. ClientCircuit de Spa-Francorchamps
  2. ArchitectLuc Nelles Architectes
  3. General contractor partnersAM Wust-Serbi

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.