Services installed in a live school environment
Texte Philippe Selke Photos Sotrelco

Not far from Mons city centre, L’Arbre Vert, a French Community special-needs primary school, is entering a new era: some of the RTG « temporary » pavilions scattered across the site since the 1960s are to be demolished following the construction of a brand-new 1900 m2 building that meets current standards. Sotrelco drew on its ability to adapt to equip the entire site with high-performance building services, connect the old system to the new one, and carry out the work without disrupting school life.
As well as installing the building services, including the electrical systems, in the new building, Sotrelco’s brief included complex work to connect the heating, gas, electricity and fire safety networks between some of the old buildings and the new wing. The project also involved buildings located relatively far apart. This meant digging 300 m of trenches between the street and the new building, and laying around 130 m of buried pipework between the latter and the existing buildings.

New boiler room and adaptation to existing systems
In the new wing, Sotrelco installed a new boiler room designed to supply the retained section of the old buildings as well. The roof is fitted with photovoltaic panels. The new building has near-passive energy performance, with just one radiator per classroom instead of 6 previously. The old boiler room was decommissioned, making it necessary to find an alternative connection point.
Thierry Maertens, HVAC project manager at Sotrelco: « The existing installation had four separate circuits in a Tichelmann loop. We did everything we could, including fitting balancing valves at the branch connections, to minimise imbalances when modifying the circuits, which could otherwise leave radiators (fitted with manual valves) in the old buildings too hot or too cold. If that does happen, and the winter of 2025-2026 will tell, these 340 radiators will need thermostatic valves. »
Sotrelco carried out most of this work during the school holidays to avoid disrupting the children. « The challenge was to be ready at the right time: open the trench, lay the pipes, pressure-test them and then reinstate everything. »

Voltage and lighting
William Chiefalo, electrical project manager at Sotrelco: « The main constraint on the electrical side was to keep the 3 x 230 V network in the retained old buildings, while ORES is upgrading its network to 3 x 400 V. We had to install transformers and make sure everything worked. »
Suitable external lighting has also been planned for installation in spring 2026, comprising 77 pole-mounted outdoor luminaires, a solution chosen to avoid glare. Given the particular layout of the site, illuminance levels are higher than average, reaching 100-150 lux in certain areas.
The new building also has a bespoke fire detection system. To avoid frightening the children, the traditional siren has been replaced by a « public address » system that broadcasts pre-recorded messages through loudspeakers distributed across the site, encouraging people to leave calmly and without distress.
We leave the final word to Laurent Van Laere, eng., Head of the Technical Services Design Office at the FW-B General Department of School Infrastructure: « This is one of the largest demolition and reconstruction projects we have undertaken within the Hainaut Regional Directorate. During the autumn break, the heating system was adapted so we could switch from the old boiler room to the new one. In addition, the most complicated task Sotrelco faced was managing the old electrical network alongside the new one. Everything went smoothly. I congratulate Sotrelco on its work; it is clear they are used to this type of project. »