Construction

Managing constraints with care and anticipating needs

Texte Philippe Selke Photos Sotrelco

Sotrelco s’est retrouvée en première ligne pour répondre à la demande d’adaptabilité des installations aux besoins de futurs utilisateurs de Biotech 5.
Sotrelco s’est retrouvée en première ligne pour répondre à la demande d’adaptabilité des installations aux besoins de futurs utilisateurs de Biotech 5.

For Biotech 5, a project firmly focused on the future, Igretec awarded the electrical works package to Sotrelco, which was on the front line in meeting the demand for installations that could adapt to future users’ needs. The installer was able to rely on numerous partners, including Niedax Kleinhuis (cable trays), Legrand (distribution solutions), Obo-Betterman (floor-mounted distribution rails), Delta Light (lighting), Eneria Belgique & Luxembourg (generator set) and Grenson & fils (lightning conductor).

Making the unknown possible

Of the building’s 4 blocks, only one had already been taken when work began. Block D (5000 m2) therefore followed a conventional approach, though the deadlines imposed by the use of European subsidies made it complex. François Dequenne: “We delivered the technical installations in just 10 months, with electrical distribution between floors via cables, as the required capacity was known. This was not the case for blocks A, B and C, where we had to anticipate future needs by proposing a modular technical solution. The Zucchini XCP busbar distribution system from Legrand Group offers great flexibility, making it easy to adjust capacity during future fit-outs without oversizing the installation.” For fire-resistance sealing, the challenge was much the same, so Sotrelco used re-openable sleeves, allowing the cabling to be adapted to future requirements.

Delivery of the main generator set, in black cladding matching the RAL colour of the window frames, for outdoor installation.

Triple power supply

Three high-voltage substations supply the installations: one 2500 kVA substation shared by blocks A and B, one 1250 kVA substation for block C and one 1000 kVA substation for block D. The installation has three types of circuit: standard, UPS-backed, and UPS-backed with a generator set as a further back-up. If the normal power supply fails, the UPS provides uninterrupted continuity, then the generator takes over, with the UPS remaining in service to ensure power quality and continuity. The generator sets run on diesel supplied from a 9000-litre tank installed inside the building. Michael Mansart, account manager for electrical works at Sotrelco, points to another specific challenge: “A regulatory issue concerning the minimum ceiling height in the car parks meant that the ORES main substation had to be moved outside, complicating electrical distribution and requiring extensive cable-tray work by our partner Niedax.”

Electrical distribution via busbar and fire-resistance sealing using Hilti sleeves: Sotrelco meets the demand for versatility with innovative solutions.

Coordination and attention to detail, from floor to ceiling

In areas cooled by SAPP ceilings, close coordination between the HVAC package, carried out by VMA and Cegelec, and the electrical works package was essential to avoid having to reopen the ceilings. Combining chilled ceilings with specialist building services required great care during installation. The same applied to fitting the floor-mounted distribution rail systems, manufactured by Obo-Betterman, which make it easy to move sockets while eliminating the need for extension leads. François Dequenne: “Precisely aligning the rails on raised floors was no easy task. The magnificent result is not something just any installer can achieve.” Sotrelco pays attention to detail even in pursuit of an aesthetic finish: at its initiative, the cable trays and fire detectors were finished in black to blend in with the colour of the corridors.

These and other examples demonstrate Sotrelco’s ability to manage a complex project with significant constraints, anticipating future needs, ensuring close coordination with other trades, and paying attention to technical and aesthetic details.

“Precisely aligning the rails on raised floors was no easy task. The magnificent result is not something just any installer can achieve.”

Question about this story? Ask your question

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction
  • CompanyLegrand
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.