Construction

A new care home for Vivalia

Les trois ailes érigées en blocs de béton sont habillées de 3 matériaux : crépi blanc, brique de couleur noir manganèse et bardage bois.
Les trois ailes érigées en blocs de béton sont habillées de 3 matériaux : crépi blanc, brique de couleur noir manganèse et bardage bois.

In an earlier issue of Construire la Wallonie, we reported on the construction by Duchêne and Moury Construct of a residential and nursing home for Vivalia in Saint-Mard (Virton). Now the two companies are back at it, again for Vivalia, building a residential and nursing home, this time in Sainte-Ode, also in Luxembourg province. Provisional acceptance took place just before Christmas.

The project involved building a new 90-bed residential and nursing home covering around 6,600 m2 in Amberloup (Sainte-Ode), to designs by Altiplan and Creative Architecture. Built on a sloping site, the T-shaped building was designed to minimise travel distances and allow for future expansion, while blending harmoniously into its rural surroundings.

The approximately 6,600 m2 building, erected on a sloping site, was built to designs by Altiplan and Creative Architecture.

Weather-related challenges

Launched in September 2020, the project was slowed down during the earthworks phase when a spring was discovered slightly uphill. Its water flooded the excavation, making it necessary to implement appropriate solutions. The spring had gone unnoticed during the soil investigations after several years of drought, before the heavens opened in 2021… Xavier Neyman, site manager at Duchêne: “In addition to the planned retention basin, we used more free-draining stone fill, then improved the waterproofing between the buried walls and the floor slabs. We built an inspection chamber inside the building to monitor rising water levels.” 

To make matters worse, excessively low winter temperatures brought the structural works to a halt, so a new completion date was agreed with the client.

Weather conditions also affected the finishing phase, but the contractors took the necessary steps to avoid further delays: “We had to heat the building with three space heaters, in particular so that the plaster could dry and the vinyl flooring could be laid. Three 5,000-litre tanks had to be refilled every two weeks, so the costs were considerable!”

The architecture is both contemporary and respectful of local traditions, creating a restful environment suited to the traditional values of older people.

Traditional construction

In construction terms, the very conventional building posed no major technical challenges for the contractors. The three wings, built from concrete blocks, are finished in three materials: white render, manganese-black brick and timber cladding. 

The roofs are a mix of flat roofs and symmetrical pitched roofs. Both contemporary and respectful of local traditions, the architecture is intended to create a restful environment suited to the traditional values of older people.

The grounds will include a vegetable garden for residents and walking paths with different types of surface. Exercise equipment has also been installed to support residents’ health. 

Provisional acceptance took place just before Christmas, with the facility due to open in spring.

Coordination and collaboration

All the work was subcontracted, as all Moury and Duchêne staff were already working on other projects. The site team: “As always, the challenge was coordinating all the trades, with close to 100 people on site at certain times. It was a real beehive of activity.”

The site team is keen to highlight the quality of its collaboration with the architects. “It was a pleasure to work with architects who were so responsive and whose follow-up was exemplary. We would be delighted to work together again, as we would with Vivalia.” 

This is another residential and nursing home for Duchêne, the second built for Vivalia, with further projects already planned with the healthcare intermunicipal association.  

Question about this story? Ask your question

Who worked on it

  1. ClientVivalia
  2. ArchitectsAltiplan et Créative Architecture
  3. Main contractorsDuchêne (Groupe Eiffage) et Moury Contruct

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.