A four-storey school building modernised in just a few months

On 20 October, the fully renovated building of Haute Ecole Louvain en Hainaut (HELHa) was officially opened on Rue Frinoise in Tournai. Work began in February 2022, and contractor Duchêne had to coordinate the project meticulously to ensure that teachers and students could return to the building for the start of the academic year.

The existing building was constructed in 1966 on the site of a former abbey. It was originally intended for an engineering school. Today, it houses courses in the Science and Technology Department (Electromechanics & Computer Technology), the Social Sciences Department (Communication & Human Resources Management) and the Health Department (Nursing, responsible for general care). In 2018, the first phase of renovation involved insulating the building externally and fitting new window frames. In 2022, Duchêne modernised the entire interior (3400 m2). Spread across 4 levels, the classrooms, staff rooms and meeting rooms are now as good as new, complemented by dining, coworking and social spaces.
HELHa’s management is clearly keen to encourage cross-disciplinary working and interaction between the different teaching departments. The ground floor houses student facilities and the various coordination teams. Ultra-modern laboratories occupy the first floor. The second floor is devoted to coworking, with flexible spaces. The top floor is dedicated to healthcare practice, enabling students to practise simulations that closely reflect the reality of a hospital setting.

A beam-and-column structure that made reconfiguration easier
Adaptability in the spirit of circular construction was not yet on the agenda in 1966, yet the building’s concrete beam-and-column structure greatly simplified the renovation, as the floor plates could be stripped back relatively easily. Devid Foubert, site manager at Duchêne: “To meet the COVID standards in force at the time, we had to aim for fairly high ventilation rates. This meant installing sizeable ducts which, in some places, were not easy to fit into the suspended ceiling.” All building services were replaced (ventilation, heating and water), with the sole exception of the condensing gas boiler, which had been replaced a few years earlier. The walls were built using Gyproc partitions, which were also used to clad the existing concrete elements. The cement tiles on the floor were replaced with epoxy resin.

The importance of good coordination
For Devid Foubert, excellent coordination was essential to meet the deadline. The project was carried out largely by subcontractors, although a few workers from Duchêne were brought in towards the end. “
“The many subcontractors had to be able to work without getting in one another’s way. At times, there could be 40 people working on the same floor. We adopted a floor-by-floor sequence, starting with demolition from the top down, then following the same approach for the subsequent stages: levelling the floors, plastering, installing heating pipes, … taking care not to lose time between the different stages.”
Duchêne did everything possible to complete the work as quickly as possible. Technical solutions were sometimes found to save time, such as using bonded plasterboard rather than plastering, which avoided several long weeks of drying time.
Question about this story? Ask your question
Who worked on it