La planification peut influencer la sécurité : l’ordre de montage a en effet une influence sur les mesures à prendre.
La planification peut influencer la sécurité : l’ordre de montage a en effet une influence sur les mesures à prendre.

When building with precast concrete, site safety can be considered at the factory stage. Safety features can be incorporated in the factory simply, cost-effectively and efficiently.

They must of course be planned into the project. The great thing here is that you put measures in place before the safety coordinator gets involved. 

Safety coordinators have been essential on construction sites for several decades. However, they only become involved in a project towards the end of the design stage. That is why designers themselves need to be familiar with the available safety solutions, so that these can be incorporated on site at an early stage. All too often, collective fall protection is still only installed once the floor elements have been laid and the concrete topping poured. That is too late, because the most dangerous work has already been completed by then! 

Guardrails

A first step is to cast pipes, sockets and recesses into the precast elements at the factory. This makes it very easy to attach rails, barriers, nets or safety harnesses during erection.

These features help make the handling of precast elements safer and can be used to secure props, edge protection and working platforms. Recesses for personal protective equipment, such as lifeline anchors, can be incorporated during production.

Safety features can be incorporated as early as the product development stage. Traditionally, elements are manufactured storey by storey, but they can just as easily be divided into sections between guardrails. As the elements extend above floor level, they also provide edge protection during the work.

If window or door openings are at floor level, edge protection can be installed in the concrete frame element in the form of two reinforcing bars. This also controls the risk of falls at door and window openings, with no need for additional measures. During the finishing stage, the edge protection can easily be ground off before the closure elements are installed.

By casting pipes, sockets and recesses into the precast elements at the factory, it is very easy to attach rails, barriers, nets or safety harnesses during erection.

Handrails

Safety can also be combined with erection by using propping systems. Push-pull props are used to position π elements, but they can also serve as edge protection for the storey above.

The π elements are transported horizontally. Before they are raised, moved into their exact position and aligned, the push-pull props and handrail supports are attached. Once the floor elements have been laid, edge protection for the next storey can be installed straight away.

Please note: depending on the site conditions, using push-pull props as fall protection is not always economically viable. The choice of construction system has a major impact on the safety measures required.

The measures required for solid concrete walls differ fundamentally from those for twin-wall elements, which still need to be filled with concrete. In the first case, propping on the inside is sufficient to position the wall. To pour concrete safely into the cavity of twin-wall elements, a platform must be installed on the outside.

Starter bars

Planning a number of measures from the outset is not only beneficial and efficient, it can also influence safety. The erection sequence affects the measures that need to be taken. For example, it is advisable to pour the connections between beams and columns only once the floor has been laid. If they are poured beforehand, the work has to be carried out at height, which is not recommended because it introduces risks such as working from ladders.

An even more efficient technique than pouring after installation is to use dry joints. These improve safety and speed up construction. Dry connections are made using sleeves, known as ‘ducts’, which need to be incorporated into the elements. Starter bars are installed in these sleeves. After installation, they are filled with non-shrink grout.

Source: CSTC, Report No. 10, Safety and installation of precast concrete elements. 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeNew ways of building
  • SubjectConcrete
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.