Circularity at scale in a major renovation

The Arch peut être considéré comme une rénovation lourde exemplaire en matière de circularité. (Image de synthèse : B2Ai)
The Arch peut être considéré comme une rénovation lourde exemplaire en matière de circularité. (Image de synthèse : B2Ai)

Following the widely acclaimed ZIN project for Befimmo, carried out in partnership with Van Laere, BPC Group is back with a spectacular, comprehensive sustainable renovation of an office building for Cores Development, again in the north of Brussels. The contractor is reaffirming its role as a pioneer in large-scale circular construction. Pierre Danner, Head of Works at BPC Group, explains what makes this exemplary project distinctive.

Built in the early 1990s, the office building due for renovation had a gross floor area of ± 14 500 m², with 11 upper floors and 2 basement levels. It had a number of shortcomings, including a low ground floor, limited floor-to-floor heights and a large number of reinforced-concrete cross-walls. In response, a pragmatic solution was adopted, retaining 70% of the structural frame while creating as many openings as possible. A double-height lobby was created on the ground floor, with an internal street linking the front and rear façades, while the cross-walls on the upper floors were opened up to create clear floor plates.

“Working as part of a bouwteam was essential to optimising both the cost and the feasibility of interventions involving the reuse of materials, such as dismantling the façade stone.”

Preparation as part of a bouwteam

The preparatory phase lasted 4 months, with BPC Group proactively managing the challenges associated with the building’s stability. Pierre Danner: “Having responsibility for the stability allowed us to respond more quickly to discoveries during the construction phase. More generally, working as part of a bouwteam was essential to optimising both the cost and the feasibility of interventions involving the reuse of materials, such as dismantling the façade stone.”

Alongside the usual constraints of a major renovation, where demolition and reconstruction are closely interwoven and trades work concurrently, among other challenges, the project also faced a series of constraints arising from its sustainable and circular ambitions. The geothermal system, for example, required some delicate deconstruction work to allow the boreholes to be drilled within the building footprint.

Another example: nearly 10 000 m2 of lime plaster was applied on the office floors. Pierre Danner: “This had a significant impact on the programme and the organisation of the work. There are few skilled workers qualified to apply this type of product, and it had to be applied as late as possible, as the plaster served as the finish.” 

Deconstruction and reuse

Doors, WCs and urinals, façade stone, raised access floors and many other deconstructed materials were stored off site for reuse, either in their entirety or after recycling, as part of the project. The lobby, for example, features a terrazzo floor made using recycled aggregates from the deconstruction, including natural façade stone and glass.  

Pierre Danner: “We are fortunate to have a client who is highly committed to sustainability, which is essential for putting these measures into practice given their additional cost compared with standard solutions. This project ranks among BPC Group’s most sustainable achievements. It is an excellent example of how a private client’s environmental ambitions can be delivered consistently and within a controlled budget.”

“A pragmatic solution was adopted, retaining 70% of the concrete structure while creating as many openings as possible.”
The raised access floors were among the many materials deconstructed for reuse.

Challenge met

Taking all these constraints, and many others, into account, the programme was tight, with the works scheduled to last 24 months. A large site management team was assigned to the project, comprising 3 site managers and 5 technicians. A major renovation of this kind requires closer coordination with the design offices so that any unexpected issues can be addressed quickly without bringing the works to a standstill. “Although we were able to obtain the original as-built drawings, we soon realised that they did not quite match the reality on site,” says Pierre Danner.

With practical completion scheduled for the end of June, the project was delivered on time and within the original budget, a real achievement for a major renovation. 

Pierre Danner concludes: “On a project like this, coordination between the parties and a clear understanding of the issues are crucial. With a client who was very open to moving things forward and an architect flexible enough to accommodate this type of intervention, things worked out well. I am quite proud of what we achieved as a team, while meeting the programme and the client’s budget.”   

The lobby features a terrazzo floor made using recycled aggregates from the deconstruction.

Belcotec: HVAC and electrical services

Having a single partner for HVAC and electrical services offers many advantages. This was once again borne out during the construction of The Arch. Belcotec acted as the central point of contact for all building services and electrical engineering. “HVAC inevitably involves significant electricity consumption. A few years ago, we therefore decided to make electrical services, including fire detection, access control, security and lighting, a fully fledged pillar of our offering, enabling us to deliver combined projects such as The Arch. It is an important reference for us, as it demonstrates that we have a firm grasp of this mix of services,” explains Stijn Geboers, HR, Finance and IT Director at Belcotec. “As this was a major renovation, it was a substantial challenge. We were already installing new services while demolition work was still under way on other floors. A great deal of prefabrication was also required, particularly for HVAC, to save time on site. And of course, large-scale renovations always involve elements that are difficult to incorporate into a theoretical 3D model. Fortunately, we were able to resolve all the issues quickly, and the project ultimately went very well. CORES Development and Studiebureau Van Reeth have already called on us several times for other projects, which shows that they were also satisfied with our contribution.”

Project details

Project Brussels: The Arch
Client Cores Development
Architect B2Ai
Main contractor BPC Group

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeBuilding with less carbon
  • SubjectRenovation
Share this article