Renovation

A heritage project where restoration and modern techniques go hand in hand

Texte Philippe Selke Photos Besix

Le rendez-vous est désormais fixé à l’automne 2028 pour le retour des premiers spectateurs dans un théâtre appelé à redevenir l’un des principaux pôles culturels de Wallonie. (photo : Corentin Haubruge)
Le rendez-vous est désormais fixé à l’automne 2028 pour le retour des premiers spectateurs dans un théâtre appelé à redevenir l’un des principaux pôles culturels de Wallonie. (photo : Corentin Haubruge)

Closed since 2015 because of safety concerns caused by the deterioration of the building, the Grand Théâtre de Verviers is now undergoing a revival. This major project, with a total cost of around €50 million, aims to breathe new life into one of Wallonia’s most iconic cultural venues while adapting it to current requirements. The work is being carried out by the Wust (BESIX), Denys joint venture, as project managers Wim Colpaert (Denys) and Pol Bartholomé (Wust) explain.

The renovation of this 135-year-old landmark has now reached a pivotal stage. After two years of work, the structural work is complete, the extension is almost enclosed and the first interior restoration work is under way. The aim is now to complete the project by summer 2027, allowing the theatre to reopen to the public for the 2028-2029 cultural season.

When the teams took possession of the building in 2024, it had been closed for nearly ten years. The lack of heating, water ingress and poor maintenance had accelerated its deterioration.

Complementary expertise

To deliver such a complex project, the two companies decided to pool their expertise. The integrated joint venture is built around a balanced division of responsibilities, with each company contributing specific know-how.

“Denys has a restoration department that seeks out this type of heritage project, while Wust brings, among other things, its experience in structural work and its specialist local teams,” explains Wim Colpaert, the site manager.

This complementary expertise has proved particularly valuable in building the theatre’s new extension, with Wust’s teams carrying out the structural work themselves.

A key feature of the project is the decision to use in-house labour as much as possible. “We deliberately prioritised Belgian and local teams. This gives us greater control over the quality of the work,” says Wim Colpaert. Restoration of the decorative features, including painted finishes, gilding and marouflage, has been subcontracted to specialist craftspeople, whose pace of work is not always easy to estimate.

For more than a year, various solutions were tested to restore the stone’s original appearance while ensuring the durability of the chosen treatment.

The inevitable surprises of a heritage renovation

As with any major renovation project, some discoveries could not be anticipated, despite the preliminary studies.

When the teams took possession of the building in 2024, it had been closed for nearly ten years. The lack of heating, water ingress and poor maintenance had accelerated its deterioration.

The main surprises included the removal of around 300 m³ of archives accumulated over the decades, as well as the discovery of dry rot in several wooden elements. “We found more asbestos than was anticipated in the original specification, but we did not uncover any fundamental problems with stability or foundations,” says Pol Bartholomé.

According to him, the estimates made during the project design phase are broadly in line with conditions on site, enabling costs to remain under satisfactory control.

A key feature of the project is the decision to use in-house labour as much as possible.

Bringing the 21st century into a building inaugurated in 1892

One of the main technical challenges is integrating modern equipment into a building that was, of course, never designed to accommodate it. Installing the HVAC systems is probably the most delicate task. “It’s a bit like trying to fit an aircraft engine into a 2CV,” says Pol Bartholomé.

New ventilation requirements, tightened since the health crisis, called for extensive engineering work to route the ductwork without damaging the historic decorative features. Installing ducts in the tier structures took several months and required various adaptations.

Another important milestone is heating the building before next winter. The recent arrival of the 800 kVA electrical transformers is essential to keeping the finishing works on schedule and protecting the future wooden elements, paintwork and restored decorative features.

Restoration of the decorative features, including painted finishes, gilding and marouflage, has been subcontracted to specialist craftspeople.

Balancing authenticity and pragmatism

Heritage restoration involves a wide range of stakeholders: architects, heritage specialists, Agence wallonne du Patrimoine, craftspeople and the client. Each intervention requires an extensive process of trials and approval. The façades illustrate this perfectly. For more than a year, various solutions were tested to restore the stone’s original appearance while ensuring the durability of the chosen treatment.

The gilding in the main auditorium has also prompted extensive discussion. “If we reproduced every historic technique exactly as it was, the cost would soon become incompatible with the available budget,” explains Wim Colpaert.

The chosen approach is therefore to adapt certain methods while preserving the appearance and spirit of the original decorative features. Several finish levels are being considered for different areas, as part of an ongoing effort to optimise the project.

Ensuring safety in a historic building

The renovation must also meet current fire safety requirements. Numerous adaptations have been made, including the creation of fire compartments and the installation of detection systems, sprinklers and fire-stopping measures. However, as is the case with many heritage buildings, some exemptions have been granted.

For example, the historic steel roof structure will not be brought fully up to current standards, as doing so would have required the roof to be almost completely rebuilt.

A specific study has nevertheless shown that the building’s many stairwells allow the public to evacuate quickly. “Simulations show that almost the entire building can be evacuated within a few minutes,” says Pol Bartholomé.

“We found more asbestos than was anticipated in the original specification, but we did not uncover any fundamental problems with stability or foundations.” (photo: Corentin Haubruge)

A next-generation cultural venue

Once renovated, the theatre will retain its historic main auditorium while gaining a new, adaptable extension. The main auditorium’s capacity will fall from around 1,200 to 1,000 seats as more comfortable seating meeting current standards is installed. The extension will provide a second auditorium with a capacity ranging from 100 to 300 seats, depending on the stage configuration.

Acoustics are also a major consideration. Renowned for its sound quality before the theatre closed, the auditorium will need to regain a comparable level of performance despite the changes made.

Tuning will continue for several months after the project is handed over, to adapt the equipment precisely to the different types of performance.

Remarkable collective momentum

Beyond the technical aspects, the two project managers highlight the collaborative dynamic established among all those involved. “Everyone is pulling in the same direction. That’s something I rarely see on a project of this scale,” says Pol Bartholomé.

Public interest also reflects the people of Verviers’ attachment to their theatre. During the latest Chantiers ouverts events, more than 1,400 visitors took part in guided tours of the site.

If the schedule is maintained, the project could be handed over in summer 2027. Around a year will then be needed for Centre culturel de Verviers to take possession of the venue, complete the stage and acoustic adjustments and prepare its programme.

The first audiences are now expected back in autumn 2028, when the theatre is set to regain its place as one of Wallonia’s leading cultural venues.

For example, the historic steel roof structure will not be brought fully up to current standards, as doing so would have required the roof to be almost completely rebuilt.

Project details

  • Client: Ville de Verviers
  • Architects: L’Escaut architectures & Barbara Van der Wee Architects
  • Main contractors: AM Wust (BESIX), Denys 

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings
  • SubjectRenovation
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.