Projects

Three modular pavilions added to Cité Modèle in Laeken

Les trois pavillons modulaires en bois ont été préfabriqués en usine, transportés vers le site et empilés sur place.
Les trois pavillons modulaires en bois ont été préfabriqués en usine, transportés vers le site et empilés sur place.

The first use of timber prefabrication in social housing

In just 14 calendar months, three modular timber pavilions were installed at Cité Modèle in Laeken, at the initiative of the SLRB. A first for social housing. Built from prefabricated modules, the buildings will provide homes for around 20 additional families, alongside the existing blocks, which are either undergoing renovation or have already been fully refurbished.

The context

The project to build these three modular timber pavilions was a Design and Build project for the Brussels-Capital Region Housing Company (SLRB). The organisation initially aimed to provide temporary accommodation for tenants of blocks undergoing renovation at Cité Modèle. Stéphanie D’hondt, site manager at Valens: “The construction also had to be quick and, if necessary, allow the buildings to be dismantled, transported and reassembled at a later date. However, because the building permit took considerably longer to obtain, the people concerned were rehoused elsewhere and the new homes became more permanent.” 

The pavilions are linked by external metal walkways.

The distinctive design

Although the 2017 tender called only for 3D construction, the final design combined 3D and 2D modules. The 3D modules, which form the wet areas (kitchen, bathroom, etc.), use a CLT (Cross Laminated Timber) structure and were prepared for the installation of specialist systems for sanitary equipment, heating, electricity and ventilation. In other words, they were pre-equipped and assembled at the Lamcol factory in Marche-en-Famenne. These 3D modules form the core of each of the three-storey pavilions, with all the living spaces (bedrooms, living room, dining room) arranged around them. These larger volumes contain very few specialist systems and are made from prefabricated 2D timber-frame panels. Each pavilion is 10-12 metres high. The total built area is around 2,500 square metres. 

The extensive use of 3D modules helped streamline transport to the site.

The main challenge

A Design and Build project of this kind naturally requires a great deal of preparatory work. “Since everything is fixed in advance and production takes place some distance from the construction site, the main challenge was to prepare and coordinate activities on site and in the factory perfectly, especially as work was carried out simultaneously, without any downtime. For example, the foundations were built on site while the 3D modules were being pre-equipped and assembled in the factory. We also had to contend with several major unforeseen issues, including the discovery of a gas pipe on the site, the impact of the coronavirus pandemic and problems with the delivery of materials. However, the speed of timber prefabrication cut the construction period in half and helped limit the disruption caused by the delay in obtaining the permit. In the end, the total construction period was just 13 calendar months, rather than the 9 months originally planned,” says Stéphanie D’hondt. 

The pavilions follow the same layout principle, with the number of bedrooms varying: an accessible one-bedroom layout, a three-bedroom layout, or a mix of one- and three-bedroom layouts.

The landscaping was not overlooked

Once the modules had been stacked on site, Valens was responsible for running and connecting the cables required in the living spaces (for power sockets, heating, etc.), cladding and finishing the pavilions, both inside and out, and completing the surrounding areas. One distinctive feature is that the internal stairs have been replaced by external metal walkways linking the pavilions. The absence of basements also makes the most of the lightweight timber construction, without unnecessarily adding weight to or complicating the foundations.    

Question about this story? Ask your question

Who worked on it

  1. ClientSLRB
  2. ArchitectBEAU, Bureau d’études en architectures urbaines
  3. Main contractorValens
  4. Co-contractor for construction, timber structureLaminated Timber Solutions (Lamcol)
  5. End user/Property managerLe Foyer Laekenois

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeNew ways of building
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.