Creating attractive places to live through village densification
Texte Philippe Selke

In Namur Province, the small municipality of Assesse (7,000 inhabitants), served by rail, has taken the initiative to gradually welcome several hundred new residents. A ZACC near the village centre is being put up for sale, paving the way for a new neighbourhood over the coming years, complete with facilities for the benefit of all residents. Under a PPP, Thomas & Piron Home will build around 132 houses and around 50 flats across 5 buildings. We take a look behind the scenes at the preparation of a project whose development is expected to span more than 10 years.
As early as 2019, the municipality of Assesse launched a competition through the Bureau économique de la Province to select a developer to develop a new neighbourhood on this site of around 11 hectares, just behind the town hall, along the Chaussée de Marche. In addition to the usual criteria for mobility, density, a range of property types and the quality of public spaces, the project had to blend harmoniously into the existing landscape and meet residents’ needs. The municipality selected the project submitted by Thomas & Piron Home, which had assembled a team for the occasion comprising urban planners (XMU), architects, landscape architects and others. As we write, following a preliminary information meeting that showed the local community’s enthusiasm for seeing the village grow in this way, work is in full swing to refine the proposal in line with the municipality’s expectations.

From competition to planning application
Alicia Golinvaux joined the developer-builder 3 years ago after completing her placement there. As a project manager, her specific remit is to assess urban development projects under PPPs and, where appropriate, support them through to the planning application stage. “I usually start when the competition is announced. I review the specifications and, if our track record is a good fit, a legal assessment is carried out. A team of specialists is then assembled to prepare a winning competition entry that is also viable. My background in geography and urban planning means I can continue to follow the project through to the planning application stage. I liaise with the municipality. In Assesse, we meet once a month to answer their technical questions and develop the project together. Meeting the criteria set by municipalities, particularly on sustainability, pushes Thomas & Piron Home to rethink some of the conventions around housing… The aim is always to sell a project we can be proud of.”
Densification connected to the existing village
As an urban planner, Xavier Mariage (XMU srl) is one of the key people behind the project. He emphasises the quality of the future neighbourhood: “The new neighbourhood will stand out for its architectural diversity, green network and high-quality public spaces. It will prioritise active travel and include public facilities and communal spaces. Given its scale, we considered the size of the new neighbourhood in relation to the village. This led us to propose facilities, a multi-purpose hall and a square at the interface with the existing village, so that new and existing residents can share a common space.”
Another key aspect is the project’s direct connection to the village centre, which itself lies along major transport links (the SNCB line to Namur and Ciney, and the N4). “So this is not a conventional case of urban sprawl, with development along a road extending out from the village!”

A project still being refined
Alicia Golinvaux notes: “At this stage, there is still plenty to optimise, particularly technical aspects relating to water management. The architectural design also needs further work.” Xavier Mariage confirms that the project is still a “work in progress”, so the visuals show only an intention, especially as needs have evolved slightly since the competition.
The new neighbourhood will be built in several phases over a little more than 10 years, allowing future residents to integrate gradually. Submitting a series of planning applications could make it possible to adapt the architecture as expectations evolve. The first planning application is due to be submitted in September-October 2025, with work starting once permission is granted, a year later if all goes well. We look forward to seeing the finished development in a few years’ time!