Dans une telle icone architecturale, les conduites et les sprinklers eux-mêmes devaient donc se faire le plus discret possible.
Dans une telle icone architecturale, les conduites et les sprinklers eux-mêmes devaient donc se faire le plus discret possible.

A visit to the 11 levels of this one-of-a-kind building confirms it: everything is atypical, from the ceiling layouts to the way each occupant has fitted out their office space, not to mention the heritage status of some communal areas and the combination of so many different functions within a single structure. From the basement to the upper floors, Le Sprinkler rationnel had to draw on its experience and show great adaptability to ensure effective sprinkler protection against fire in every nook and cranny.

The pipes run through areas with “waffle” ceilings, requiring precise setting-out to align them as elegantly as possible with the structural elements.

Founded in 1982 and certified to ISO 9001, VCA and BOSEC, Le Sprinkler rationnel has specialised for more than 40 years in the design and installation of sprinkler fire protection systems. Its services range from feasibility studies, engineering with 2D and 3D drawings and hydraulic calculations, and pipework prefabrication in its own 2000 m² workshops in Brussels or in collaboration with long-standing partners, to the installation of networks and maintenance of these systems. 

“Wherever there’s a sprinkler system”

The company installs all types of sprinkler systems (wet, dry, pre-action, deluge, …) and water supplies in any building where they are required, including offices, car parks, hotels, industrial buildings, warehouses, pharmaceutical and petrochemical facilities, and nuclear sites.

Benoit Poupart joined the company founded by his father in 2005 and works there as a Project Engineer alongside around fifteen colleagues. He oversaw the “Royale Belge” project from start to finish while completing another megaproject: the BNP Paribas Fortis headquarters on Montagne du Parc in Brussels. His extensive experience with large-scale projects was invaluable in eliminating any guesswork on a project as complex as the Mix and the various functions it accommodates. 

“We proposed different installation approaches, for example using existing openings in the beams, as well as different finishes and colours for the sprinklers and pipes in areas where bright red would not have been aesthetically desirable.”

Atypical in every respect

Benoit Poupart: “It’s truly unique to have offices, a hotel, coworking spaces, car parks, restaurants, archives and various plant rooms all in one building, some of which is heritage-listed. What’s more, it’s a high-rise building, with the specific fire protection requirements that entails. The existing building had sprinkler protection only in a few isolated areas, and we were the ones who carried out that work at the time.”

This architectural icon is an interesting mix of concrete and steel structures, particularly in its renovated atrium, which includes heritage-listed elements. The pipes and sprinklers themselves therefore had to be as discreet as possible. “We proposed different installation approaches, for example using existing openings in the beams, as well as different finishes and colours for the sprinklers and pipes in areas where bright red would not have been aesthetically desirable. This takes a little more preparation in the workshop, but we aim to blend in as well as possible with the existing building.” The building is also atypical in another respect: flat ceilings are a rarity. There are changes in level everywhere, which the pipes and service ducts have to follow, as well as areas with “waffle” ceilings, requiring precise setting-out to align the pipes as elegantly as possible with the structural elements.

The water supply for the entire sprinkler system is located in a very small basement plant room.

Flexibility and adaptability

The company’s experience, together with its practice of prefabricating the entire installation in its workshops, enabled it to manage the countless changes that arose during construction. For example, although the office floors were initially planned as open-plan spaces throughout, each occupant ultimately fitted out their space in their own way, adding numerous partitions or “rooms within rooms”. This changed the layout of the sprinkler distribution. So there was no copying and pasting from one floor to another, or even from one wing to another: each area was a project within the project. The hotel section of the Mix is also atypical, with a mix of different room types on every floor.

Work began in late 2021, and the project soon became a collateral victim of the war in Ukraine, with shortages and soaring prices. To keep work moving and meet delivery deadlines, Le Sprinkler rationnel stockpiled large quantities of materials. As construction progressed, the original order was supplemented with orders for other areas of the building, including the vast basement levels, where archive rooms required a higher level of protection than initially anticipated.

“We always prefabricate in our workshop, and that is our strength. On this project, it proved particularly useful when we had to increase the pace of work. We standardised the pipework lengths as much as possible so that we could cut entire bundles of pipes, up to 60 at a time, in a single operation. We then delivered the materials to site, area by area, sometimes bringing them in through very narrow openings or passages. The large team we mobilised for the on-site installation enabled us to fit the networks in different areas in parallel.”

Le Sprinkler rationnel prefabricated the pipework in its own 2000 m² workshops in Brussels.

As the project evolved over time, the other building services also had to adapt. Since sprinkler coverage must not be obstructed, several areas required multiple studies as the project developed, including coordination with the ventilation ducts, to avoid having to redo the installations on site. More generally, coordinating with the other contractors on site required close attention, but everyone was highly cooperative and aware that they were contributing to a project that would attract attention.

Drawing on his experience, Benoit Poupart shared the problem areas with the inspection body ANPI at an early stage to find suitable solutions. In the end, the handover resulted in only a few minor comments, which were dealt with quickly and easily despite the variety of conditions and the scale of the project. As evidence of the client’s satisfaction with the work, they have already asked Le Sprinkler rationnel to carry out further studies for other areas of the building.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeBuilding and site safety and security
  • SubjectProjects
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.