Iris Tower (formerly Silver Tower): the challenges of a high-rise construction project

A construction project such as the Silver Tower, renamed Iris Tower, near Brussels-North station, is quite exceptional in Belgium.
The tower, with 33 storeys above ground and a height of 136 m, is elliptical in shape. The project occupies a small plot of land, hemmed in between busy traffic routes and railway lines. Taken together, these factors piqued our curiosity. And with good reason, it seems: both the manufacturer of the concrete elements and the contractor said they had risen to the challenges through excellent preparation, a number of ingenious solutions and good cooperation.
The scene is set straight away when Pieter van der Zee, technical director at CRH Structural Concrete, points out that a 100 m-high building is not necessarily a tower: “It all depends on the ratio between the footprint and the height. You could build a 100 m-high building, but if it is also 100 m wide and deep, it is not a tower!” The Silver Tower is indeed a tower. So we can keep asking questions of Pieter van der Zee, as well as Guy Lambrechts (project engineer for the Silver Tower project at Ergon nv in Lier) and Yves Uyttenhove (site manager at CIT Blaton sa).
FEBE: Let’s start with the fundamental challenges: the shape, the height and the site. To what extent did they present obstacles to overcome?
GUY LAMBRECHTS: “The height itself is not the biggest challenge. Under Belgian standards, this is indeed a high-rise building. But whether you build ten, twenty or thirty storeys, the columns are sized and reinforced accordingly. In the end, you carry out the same calculations at any height, and the basic issues remain the same. This small site in a busy traffic area is another matter altogether. A staircase was installed over the lorry loading and unloading areas to direct staff to the site. Everything was planned very carefully. The lower storeys took six days each to build, but the upper storeys could be completed in 4.5 to 5 days. When designing the precast elements, you also think ahead to how they can be erected efficiently. This building has 21 columns per storey. We produced columns spanning two storeys. Once these double-storey columns are installed, you are already ahead on the next level, where you only need to install beams to complete the storey. We could not use this technique for two main columns, because it would have had too great an impact on their design. They would have been too heavy, negating the efficiency gains from faster installation.”
YVES UYTTENHOVE: “For us as the contractor, logistics and planning are the key challenges, as Guy pointed out. With such a tightly organised schedule, even a slightly delayed delivery affects the entire day’s programme. Alongside the very rigid planning, safety becomes an even greater concern than usual: many people are working together in a small area, the impact of any falling object is greater, and more equipment has to be moved because there is little room to manoeuvre. Sometimes an extra traffic lane also has to be allowed for to organise everything. On a typical site, someone might spend 25% of their time on logistics, whereas here it can be as much as 50%.”

FEBE: You have a great deal of experience to draw on. Is an elliptical shape always an additional challenge?
PIETER VAN DER ZEE: “A few years ago, we built some truly elliptical buildings, such as the Ellipse Building and Covent Garden Tower, also in Brussels’ North Quarter, using elements supplied by Ergon nv. This building is not an ellipse, but is made up of two circular arcs placed against each other, which is less complex in itself.”
YVES UYTTENHOVE: “An elliptical building has a major impact on the construction site. The surveyor has to keep measuring and setting out points. You have no right angles to work from, so you cannot set out a straight axis. The surveyor is therefore on site all the time, and this also calls for good planning.”
GUY LAMBRECHTS: “The shape of a project has a huge impact on the production of the elements. The external façade beams all follow the curved shape. Such elements require more design work and are complex to form. With an ellipse, the radius changes continuously, and the curvature of the elements varies even more. Here, we were able to work with the same radius throughout the building and therefore use the same formwork for all the columns and beams, adjusting only their length.”
“This also affects the hollow-core slabs. Since the building is curved, a solution is needed to ensure that the floor elements ultimately follow its shape. Either each hollow-core slab has to be laid at a different radius, or they are laid in a straight line, leaving a corner uncovered at the end (see photo). This so-called pie-shaped piece was initially intended to be cast in situ. We came up with a precast solution: an element with the structure of a lattice girder slab, connected to the hollow-core slabs on both sides by reinforcement. This saved us a great deal of formwork and propping. We are constantly looking for alternatives like this. From the tender stage, we are already thinking about how to optimise the whole building and make construction easier and cheaper. Even at the weekly site meeting, questions always come up that we need to find better solutions for. For elements to be cast in situ, we consider whether precast solutions could speed up construction. After all, factory production is possible whatever the weather, allowing us to get ahead of schedule. That means we can work even faster.”
FEBE: What other precast solutions make the building special?
PIETER VAN DER ZEE: “The connection for the V-shaped columns at the entrance was initially designed differently, but it was practically impossible to build. We looked for an easier connection. As a result, each column had a different base and head. We solved this during production using individual, highly accurate EPS (expanded polystyrene) moulds, which were replaced in the formwork each time. This meant every column arrived on site with exactly the right head and base.”
GUY LAMBRECHTS: “The curved shape of the building itself also posed an additional challenge for these columns. Because of the curved shape, the heads and bases of adjoining columns are not in the same plane. In this case, being able to visualise the structure in 3D using a programme such as Tekla is a real help.”
FEBE: Could precasting also be used for the basement?
YVES UYTTENHOVE: “No. We excavated the 8 basement levels using the Stross method, which is not suited to precasting. With the Stross method, a floor slab is cast at level -1, anchored into the diaphragm walls. An opening is made in it, two openings measuring 5 x 8 metres in this case. Through these openings, the soil beneath the floor slab is excavated using a crane and a tracked loader. Once the level has been fully excavated, a floor slab is installed, also anchored into the diaphragm walls, with new ‘Stross openings’ made in it to excavate the next level. We continued in this way down to level -8.”
“Thanks to the diaphragm walls, which form the deep foundations of the building, construction above ground can also proceed at the same time. Above-ground construction is faster, too. By the time we had reached level -8, 24 storeys had already been built above ground.” “For me, level -8 was also a first, as I had never gone deeper than 5 levels using the Stross method. This project was certainly a major challenge in that respect. Ventilation, propping the external walls, work with hydraulic jacks at level -7 to maintain the building’s stability, access: to name just a few, these were all quite exceptional conditions.”

FEBE: How do you organise logistics when you only have two lorries and still have to carry out in-situ concreting?
YVES UYTTENHOVE: “Good logistics require good planning. For the above-ground levels, we prioritised precasting for the sake of speed. You focus on that, then organise everything else around it. I compare the logistics of a complex site like this to those of an airport. It is essentially about managing your ‘airport’ or construction site as a whole: you know which flights are taking off and landing, just as you organise the deliveries that have to arrive on site. Communication is crucial to turn the overall plan into a more detailed one. When a load arrives on site, you need to know exactly what it contains, where it has to go, how it will be unloaded and when it has to leave again. With a schedule this tight, anything is possible, even on such a small site.”
Wind load challenges
FEBE: When sizing the elements, do you have to take into account the fact that they will be installed at considerable height, for example, to withstand additional wind loads?
PIETER VAN DER ZEE: “Wind loads certainly affect the façade and the core, but not the precast elements on this project. They can, however, be exposed to very strong winds during installation. The lifting loops have to be very stable and positioned with great precision relative to the centre of gravity.”
GUY LAMBRECHTS: “To absorb the additional wind loads, the engineering firm Greisch designed braces connecting the core to the façade at the seventeenth and eighteenth storeys. These braces increase the lever arm of the lower storeys. They incorporate movable hydraulic jacks to absorb the wind loads. The braces are fixed to the core on one side and to the façade columns on the other, which meant our columns had to withstand additional compressive and tensile forces and therefore needed extra reinforcement. This intervention meant the core at the lower storeys did not have to be made even more massive.”
FEBE: We were told that the rounded shape could cause a kind of twisting and that you had a special solution for this.
PIETER VAN DER ZEE: “In principle, curved beams would be needed, but since prestressing is always in a straight line, a curved beam does not make much sense. We came up with a special Z-shape to control the centre of gravity of the prestressing and prevent the beams from deforming.”
FEBE: Are there any other optimisations that could inspire your colleagues?
GUY LAMBRECHTS: “One optimisation I am proud of is the Y-shaped element, which allows the façade to step back over several floors, creating a spiral shape from the 25th floor onwards. The ‘arm’ extending towards the façade was originally 250 mm in diameter and connected to the 500 mm diameter base section. After discussion, we decided to make the arm tapered. This made the transition between the main axis and the lateral axis more aesthetically pleasing and created a visually attractive feature.”