E42/A15: Huccorgne viaduct works: Bridge carrying the Liège-bound carriageway, now refurbished, to reopen on 27 July

At Wanze, the first half of the Huccorgne viaduct (E42/A15) refurbishment project will be completed on 27 July. The bridge that normally carries traffic towards Liège will have been fully renovated and will reopen to road users. This major project, with its many technical challenges, is therefore on schedule. The same work will be carried out on the second bridge from January 2023.

Work on this section of the viaduct began last January. The final operations will be carried out over the coming weeks: laying the last layers of surfacing, followed by road markings and the installation of various items of equipment. Numerous technical challenges have had to be overcome during these 6 months of work.
APPROACH SPANS: INSTALLATION AND REMOVAL OF GIRDERS
In total, during this phase, which focused on the bridge that normally carries traffic towards Liège, 36 girders, each weighing 60 tonnes and measuring 30 metres long, were handled in lifting operations carried out at heights of up to 60 metres.

Thanks to the teams’ work, and despite sometimes windy weather, the replacement was completed on schedule, in just under a month. Removal of the old girders began on 15 February. The final girders were installed on 10 March.
Each of the new girders, precast in a factory, was brought to the site as an abnormal load. Installing them was a major step, as it made it possible in particular to adjust the vertical alignment of the structure, improving comfort for road users.

Previously, 4,350 m² of bridge deck had been sawn, demolished and removed, amounting to a total of 1,950 tonnes.
In the following months, 4,350 m² of precast deck slabs were installed, 180 tonnes of reinforcing steel were cut, bent and installed, and more than 650 m² of concrete was poured.
CENTRAL SECTION: MOBILE SCAFFOLDING AND ENHANCED PRESTRESSING
For several weeks, the central section of the viaduct became an “island” surrounded by open space. Once the deck had been completely stripped back, with the various items of equipment and the surfacing removed, mobile scaffolding was erected on the central viaduct to carry out the necessary repairs to the outside and underside of the box girder.
To meet the ever-increasing demands placed on structures as the weight of vehicles permitted on our motorways rises, the load-bearing capacity of the central viaduct has been upgraded. Six prestressing cables have been added to each of the 2 viaducts. Each cable was tensioned to 360 tonnes, providing an additional 2,160 tonnes of prestressing force per bridge.


BACKGROUND
The project involves refurbishing the Huccorgne viaduct, which carries the E42/A15 motorway at Wanze. Specifically, the work will give the viaduct, which consists of two bridges, one in each direction, a complete makeover:
Ø The approach spans of both bridges will be demolished and rebuilt, except for the piers, which will be retained and repaired;
Ø The central section will be refurbished;
Ø The project also includes adjusting the vertical alignment of the structure to improve comfort for road users, reviewing the prestressing, installing new waterproofing and surfacing, fitting noise barriers and LED lighting, installing steel structures to facilitate future inspections (walkway), and fitting a metal grating between the 2 viaducts.
For further information:
210622-e42a15-viaduc-de-huccorgne-rehabilitation-lancement-cp.pdf (sofico.org)


One of the project’s biggest challenges is carrying out this extensive work while minimising disruption to road users. The viaduct carries an average of around 60,000 vehicles a day (both directions combined), rising to 2,500 to 3,500 vehicles per hour at peak times (both directions combined).
To minimise the impact on traffic, 3 major phases (4 months, 6 months, 6 months) have been planned on the bridge decks (the upper surface of the structure) through to July 2023, with the lanes reopened during the second half of 2022:
- From 2 August 2021 to 19 November 2021: strengthening of the bridge towards Namur to allow 2 lanes of traffic to be maintained in each direction during the next phase (completed).
- From 10 January 2022 to 27 July 2022: work on the bridge that normally carries traffic towards Liège;
- From August 2022 to January 2023: work will continue under the viaduct, on the piers supporting the structure (normal motorway traffic conditions);
- From 9 January 2023 to 19 July 2023: work will be carried out on the bridge that normally carries traffic towards Namur.
During the various phases of work on the bridge deck (the upper surface of the structure), the general plan is to maintain 2 lanes of traffic in each direction on the motorway, with a maximum speed limit of 50 km/h.
Below the motorway, Rue Robiewez and Rue Famelette have been closed from 2 August 2021 to 2 August 2023. A diversion is in place via the N652/Route de l’Etat, Route de Lavoir and Rue Biénonsart.