Building and extending 5 car parks at the same time: quite a challenge!

Une durée de chantier de 23 mois est prévue pour le parking P12, destiné au personnel (1 110 places – 5 niveaux).
Une durée de chantier de 23 mois est prévue pour le parking P12, destiné au personnel (1 110 places – 5 niveaux).

In 2016, Liège University Hospital issued a call for tenders for the construction and extension of 3 car parks at Sart Tilman and the extension of 2 car parks at the Bruyères site.

The 6nergy Park consortium was selected for this major project. Leading this cohesive, multidisciplinary team is Sprimont-based company ELOY, working with DEMOCO. The aim is to increase the number of available spaces from 2,045 to 3,660 within a year.

Cédric Nils, DBFM (Design, Build, Finance, Maintain*) Manager at ELOY, explains what the project involves: « The three new car parks at Sart Tilman, for staff, patients and people with reduced mobility, share the same construction method: demolition of the existing at-grade car park infrastructure, installation of retaining walls, excavation, construction of a column-beam-hollow-core slab structure with a compression topping, steel access walkways and metalwork, followed by resin flooring. The car parks at Bruyères are extensions to existing at-grade car parks. The work there will therefore mainly involve roadworks. »

Work will begin with construction of the visitor car park, P9 (494 spaces, 5 levels). It will take 13 months.

A major construction project

Building five car parks at once within a fairly short timeframe is a huge undertaking. « It is certainly not every day that you get started on a project on this scale in these conditions, » acknowledges Cédric Nils. The constraint of working on operational hospital sites had to be taken into account both during the project’s development and its delivery. « During the works, a minimum parking capacity must be guaranteed, access to the site must be as safe as possible, and emergency vehicle movements must be maintained. The presence of a heliport, an essential link on the site, also calls for specific safety measures. »

Other challenges

On top of that, there is the flow of people regularly using the University’s facilities, and the fact that other projects will be taking place at the same time on both sites: roadworks, renovation of the glass roof and emergency department tower (Sart Tilman), and a new care unit with changing rooms and workshops (Bruyères). « These various factors make construction, straightforward at first glance, more complicated, particularly when it comes to delivering structural components, » explains Cédric Nils. Other challenges arose during the design stage: « The main one was to combine the available areas, level constraints and the minimum capacity required for each car park, whether or not it was in a structure. » 

Fortunately, the project partners can draw on considerable experience. ELOY has recently delivered, for example, the Verlaine motorway service areas, the multi-storey car park at CHU in Esneux and a landscaped car park for the University of Liège at Blanc-Gravier (Sart Tilman).

Work on P1 (1,105 spaces, 3 levels) will begin as soon as work on P9 is complete.

Effective collaboration, already put to the test

The 6nergy Park consortium includes Optimal Parking Control (car park operator), architectural practices Herbiet Grosch Architectes (HGA) and Atelier d’Architecture du Sart Tilman (AAST), engineering consultancy Lemaire (BEL), responsible for structural engineering and building services, and Semaco, which is handling site organisation and planning. Cédric Nils says: « OPC agreed to put its trust in us and take on the challenge, despite competition from some of the ‘heavyweights’ in the car park sector. I am convinced that this choice has paid off, since the operator has adapted its way of working to the CHU’s requirements rather than trying to impose the reverse. » The architects had already worked with ELOY on both external and internal projects. In addition, as its name suggests, AAST is the ‘local expert’ and has an almost exhaustive knowledge of the site. HGA also brings clear complementarity in its architectural approach and urban vision. Engineering consultancy Lemaire, meanwhile, had a strong track record in car parks and a good knowledge of the other team members. Since each partner was able to hear from the outset that its proposal could be improved, the collaboration has been excellent. Every partner will have plenty to do, given the project’s very tight schedule.    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectProjects
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.