An exemplary renovation and conversion on every level
Texte Philippe Selke Photos Crolle Agency

Thomas & Piron is a major player in renovation too. The Bara project in Anderlecht, winner of Renolab 2021, is further proof of this. This complex project, a stone’s throw from Brussels-Midi station, aims to convert 3000 m2 of former industrial buildings into 27 social housing units and 3 communal and green spaces dedicated to children, training and leisure. Victor Spinazze, site manager at Thomas & Piron Rénovation Bâtiment, tells us all about this project, which sets an example both socially and environmentally.

The Bara project is due for completion in September 2024. Located within a city block, it consists of three buildings that were originally connected. Major demolition work has separated them. Work on Building C, furthest from the road, is the most advanced, with pre-handover inspections imminent. In Building B, the new screeds have been poured and tiling is under way. Building A is the least advanced. It originally comprised a house divided into flats, with timber floors and stability issues. The first internal plasterboard partitions are being installed, along with the service runs. As well as converting the existing floors, each building is being extended upwards using a timber structure with prefabricated insulated panels. Building C’s roof is distinctive in that timber panels have been added to the existing sloping steel structure, while the other two buildings have flat roofs. On the existing floors, the aim is to retain as much of the original fabric as possible, creating a new structure around the load-bearing elements, usually the stairwells or lift shafts. No load-bearing elements are being demolished, but the openings are being adapted to meet housing regulations.

A challenging location
Victor Spinazze identifies the site’s main constraint. “The project is entirely within a city block, with no way to access it by vehicle or machinery, and Rue Bara is congested at all times of day. Deliveries are therefore particularly difficult, and everything has to be moved inside the building by hand. While looking for the best place to position the tower crane, we discovered cellars, which first had to be filled in. Bringing in crushed stone was out of the question, so we filled them by blowing in Argex.”
“We made sure to work with trusted partners who specialise in renovation, including for specialist building services. Our own workers carried out some of the structural work, but here too, the lack of access for machinery greatly increased the amount of labour needed for handling materials, so we also had to use subcontractors.”

Fire resistance and technical priorities
For a residential site within a city block, the fire service’s fire-resistance requirements are quite demanding, meaning extensive work is needed on compartmentation, access routes and fire detection. “In this kind of renovation, we have to deal with concrete structures that do not initially meet fire-resistance requirements and therefore need protecting. The work sequence has to be adapted compared with a new build, because services such as electrical installations need to be installed much earlier, before fire protection is applied, for example to suspended ceilings. We therefore finish by installing the internal partitions that do not need to be fire-rated. Whether we work with Gyproc, Siniat or Knauf, we always consult them beforehand to review all the technical junctions and establish the order of priorities between thermal and acoustic performance.”

Sustainability concerns
From the start of the project in August 2022, Thomas & Piron Rénovation Bâtiment worked through the architect with BatiTerre, among others, who came to salvage the best radiators and marble fireplaces. In turn, the contractor used some of BatiTerre’s materials, particularly for the street furniture around the site, whose surroundings are very green (Thomas & Piron worked with the non-profit organisation Nos Pilifs on this). Victor Spinazze explains: “We also tried to use reclaimed tiles, but ran into a problem with the warranty for the system used. In the end, we had to use new materials. This is an area that is set to evolve to make circular initiatives easier. We went to great lengths to insulate the buildings, reinsulating all the structures, either using timber panels or externally. This was complemented by triple glazing, photovoltaic panels on all the roofs, green roofs, heat pumps and rainwater harvesting tanks, … We even plastered walls with clay from excavations at Brussels construction sites…” All this caught Renolab’s attention. There is a real desire to go a step further in terms of energy performance. Sustainability in construction waste management was not overlooked either, even though the lack of access made it more difficult. Nor was the impact on neighbours insignificant, despite the communication and mitigation efforts made.

RenoBat goes hand in hand with Renolab
It is clear that Bara has earned its Renolab support. The constraints and challenges of renovation have been successfully overcome thanks to rigorous coordination and close collaboration between the various partners. The Renolab project also demonstrates Thomas & Piron Rénovation Bâtiment’s commitment to sustainability and innovation in renovation.
Question about this story? Ask your question
Who worked on it
- ClientLes Deux Châteaux (Exploitant : Les Petits Riens)
- ArchitectNest Architects
- Main contractorThomas & Piron Rénovation Bâtiment
Keep following this
Get an email when a new story is published. No account needed.
- ThemeRenovating existing buildings
- SubjectProjects
- CompanySiniat