Strebelle’s vision lives on in Belgium’s largest student housing project
Texte Philippe Selke Photos Quares

On the Sart-Tilman campus, the U-KOT project, led by the Life, Ethias, Les Entreprises G. Moury, Quares consortium, has moved into the renovation phase after students relocated to the newly completed buildings. The programme includes the construction of around 400 student rooms spread across 7 buildings arranged in an ellipse, as well as the renovation of 362 others, built in the Brutalist style in 1968. This is the largest project ever undertaken by Gilles Moury as sole main contractor, with a budget of more than 40 million euros.
Delivered under a DBFMO contract for the University of Liège, this major project is based on a works concession covering the design, construction, renovation, financing, maintenance, management and operation of the accommodation over a period of 65 years.
The new part of the project (B13x) provides more than 400 student residences of various types, including rooms with or without en-suite facilities and studios. These are complemented by numerous shared spaces, including reading, games and sports areas, rooms with washing machines and tumble dryers, a large garden and a multi-purpose room that can serve as a student bar.
The existing B13 complex is an iconic Brutalist ensemble from the late 1960s, designed by André Jacqmain. It is being fully renovated in keeping with its distinctive design, while providing the level of comfort expected by today’s students. It comprises a low-rise building with an entrance hall, shared spaces, two apartments for visiting lecturers and plant rooms, flanked by three towers, each with 120 rooms.

A dialogue between architectural heritage and modernity
The project is distinguished by a unique combination of heritage architecture and new construction. Frederik Vaes, an architect at UAU collectiv, explains how this legacy was handled: “We drew inspiration from the master plan designed by Claude Strebelle at a time when designers enjoyed a degree of freedom far removed from today’s restrictions and constraints. The Brutalist, monumental buildings of Sart-Tilman are remarkably well integrated into nature. We wanted to carry on this philosophy, with people and nature at the centre, by building on a site that allowed us to preserve a woodland area and where the slope softens the buildings’ imposing appearance. We chose an elliptical shape for the same reason. By cutting through the ellipse at strategic points to create 7 volumes, we opened up views and established connections with the wooded surroundings. A building dating from 2018, with no architectural value, sits at the centre of the ellipse, dividing the central courtyard into two distinct spaces.”
Movable aluminium sunshades create a distinctive pattern on the façades, displaying the colours of Claude Strebelle’s master plan. As a result, the complex never looks quite the same from one viewpoint to another.


A project delivered in two main phases
Work began on 1 April 2024, followed by a “first stone” ceremony at the end of May. G. Moury was able to hand over the new student residences in early February 2026, allowing students to leave the old buildings and move into the brand-new complex. Renovation of the old buildings began immediately, with handover scheduled for September 2027.
Careful management of environmental constraints, optimisation of energy performance, technical mastery of large-scale volumes and close coordination between the various trades: this project draws on the full technical and organisational expertise of the Les Entreprises G. Moury, GM teams. A hierarchical structure that allows for extensive delegation of authority supports responsiveness and rapid decision-making.
This huge project is being carried out almost entirely by subcontractors, including Moury Group companies such as Défi for HVAC and Mosabois for joinery, as well as external partners such as Charlier Numelec for electrical work and Atelier 23 for painting. Moury’s site management team comprised part-time technical director Philippe Lelotte, two site managers and an assistant site manager.
Managing the project required close coordination between the various trades and subcontractors, with the workforce reaching up to 130 workers during the finishing phase.
The new complex is built mainly from precast concrete, with very little cast in situ. The buildings’ curved forms required precise setting-out by a surveyor and the use of smaller precast elements to create the curved sections. Combining function and aesthetics, sliding sunshades add a splash of colour and give the buildings a strong visual identity.

Pace and expertise
Nicolas Lelotte explains: “The biggest challenge was undoubtedly meeting the deadline and maintaining the pace it required. Work was originally due to start on 2 January 2024, but was postponed until 1 April because of appeals and the time needed to obtain permits. The existing buildings’ accommodation leases were due to expire contractually on 1 February 2026, so we had to meet that deadline to allow students to move into the new complex. The challenge was therefore to find subcontractors and suppliers able to keep up with the pace and meet the schedules we set them.
Managing all the parties involved while complying with planning criteria, fire safety requirements, EPB standards, and everything required for BREEAM certification, such as material traceability and the project’s environmental impact, took considerable effort and expertise. The aim is to achieve BREEAM Very Good certification, with WELL certification also a possibility in future, which would be rare for student accommodation. The acoustic requirements were particularly demanding, with double-leaf walls and strict specifications to ensure students’ comfort.”
At the time of writing, renovation work has begun on the 1968 buildings to bring these energy-inefficient structures up to current standards. The renovation is being carried out from the outside, which raises architectural considerations when it comes to preserving the original appearance and Strebelle’s vision as far as possible.
In conclusion, U-KOT is a major challenge successfully met thanks to the expertise of Les Entreprises G. Moury, GM and its partners. Every stage is designed to combine quality workmanship, sustainability and harmonious integration into the natural setting of Sart-Tilman. The students are lucky!


Project details
- Client: University of Liège
- Architects: Studio Sart: UAU collectiv (design) and Altiplan architects (delivery)
- Main contractor: Les Entreprises G. Moury, GM