Prestressed hollow-core slabs for the roof of Pairi Daiza’s new entrance

Les hourdis précontraints ont été utilisés comme plancher de toiture de la nouvelle entrée de Pairi Daiza. (photo : Dherte)
Les hourdis précontraints ont été utilisés comme plancher de toiture de la nouvelle entrée de Pairi Daiza. (photo : Dherte)

In March 2022, Nerva (Rector, Lesage group) supplied 3,600 m2 of prestressed hollow-core slabs to the site in Brugelette from its plant in Harelbeke. The general contractor, Dherte, used them for the roof floor of Pairi Daiza’s new entrance. Well-organised logistics were one of the keys to meeting the deadlines.

Patrice Rasseneur, technical sales representative at Nerva: “We regularly work for Dherte and other class 8 contractors, because our prestressed hollow-core slabs are designed for large-scale projects. They are 120 cm wide. For this project, their maximum length was 12.75 metres and their thickness was 27 cm, but we can supply slabs up to 18 metres long and with a maximum thickness of 40 cm.”

Well-organised logistics were one of the keys to meeting the deadlines. (Photo: Nerva)

Closing off the shell with concrete hollow-core slabs is financially advantageous and also offers fire safety benefits. For flat roofs, the required fire resistance was one hour, in accordance with the standard.

Dherte chose Nerva slabs not only for their price, but also for the manufacturer’s ability to deliver on time, as the deadlines could not be changed. For the Belgian manufacturer, the project involved nothing out of the ordinary in terms of production, as the slabs only had to support the weight of the roof covering. 

Efficient design office and logistics service

Nerva can rely on its in-house design office to draw up a general laying plan, which the contractor uses to schedule deliveries in line with the progress of the work. A specialist at Nerva then plans the deliveries, ensuring that the elements are loaded onto the lorries in an order that makes installation easier and maximises efficiency on site. As the general contractor moved at speed on the shell of the park’s new entrance (see previous article), deliveries of hollow-core slabs followed one another at a brisk pace throughout March 2022. The plant in Harelbeke is only 75 km from the park and is well connected to the motorway network, which helped.     

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.