New station, Mons | Intermodality and permeability, the guiding principles behind Mons’s new station

The new station in Mons, designed by Spanish architect Santiago Calatrava, is scheduled to open in 2020. With just over a year to go, how is this exceptional project progressing? Construire la Wallonie takes a look.
Elisa Roux, spokesperson for SNCB (the project client), explains at the outset: “This is not simply a new station, but an entirely new railway site, with works extending over some 2 km.” Mons station, the 16th busiest in Belgium and the 5th busiest in Wallonia in terms of passenger numbers, opened in 1841, was demolished and rebuilt in 1952, then demolished again in 2013, after SNCB decided to refocus it primarily on passenger services. Euro Liège TGV (Eurogare since 2010) was commissioned to carry out the studies and oversee the works. The project notably involved reducing the number of sidings and freight loops to make better use of the site’s commercial potential and passenger facilities, and standardising the platforms’ length and width. “It also meant substantially altering the alignment of Line 118, the ‘Walloon backbone’, to increase the speed of entry into the station to 90 km/h,” explains Frédéric Sacré, spokesperson for Infrabel, the other project client. In this context, it proved impossible to retain the existing building. The sixty-year-old station is therefore making way for a (future) large white dragonfly, spanning the platforms and providing access from both the front and the rear. The new station is intended to deliver greater intermodality, as well as permeability, restoring a link between neighbourhoods that had been severed by the railway.

A key station for Mons
Elisa Roux: “The future station in Mons will serve both rail and road transport. It will have five straight platforms and twelve tracks, seven of them for passenger trains. Three platforms will be exclusively for rail, while the other two will be shared: the first by trains and buses, the second by buses, private vehicles and taxis. The station will be accessible from both sides, with an underground car park integrated on each side of the site, providing 858 spaces in total. The station bridge, which links the two sides of the railway site, will channel passenger flows towards the various platforms and house passenger services and local shops. Passenger numbers will rise significantly thanks to TEC passengers boarding and alighting at the station platforms.” The benefits for the city of Mons will be positive, as mayor Nicolas Martin explains: “It is only natural that a city of Mons’s size and importance should have a station that is not only attractive, but also modern and multimodal. Mons is a strategic transit point, ideally located close to both the French border and the capital. The station is the first impression visitors have of Mons, so it needs to match the beauty of our city. It will also be a link between the historic heart, with the city centre and its heritage, and the modern city, where you will find the administrative centre, the congress centre, Digital Innovation Valley and more. Both areas are undergoing change and benefiting from major investment in key infrastructure.”

Everything depends on the bridge, and beneath it
The station bridge spanning the site is “sheltered at either end by a canopy and separated from the outside by automatic doors,” explains Elisa Roux. “Its external covering consists of panels and glazing, and it is topped by a movable roof lantern. Platform shelters are attached on either side of the bridge and cover the platforms along their entire length. Finally, with its twelve lifts and fourteen escalators, the station has been designed to provide optimum accessibility for people with reduced mobility. To build the station bridge’s steel frame, sections were assembled away from the railway site and then progressively launched over the tracks, in order to minimise disruption to train services. Temporary sliding and support trestles were installed on the tracks and platforms for these operations. Following the seven launching operations, the bridge reached its final position across the site. Once the current operation to lower the structure is complete, it will rest on its columns and the temporary trestles will be dismantled. The structure is being transferred onto its permanent supports in stages, with loads carefully monitored as it is lowered. This is a critical operation, as it determines whether other works can begin or continue.”
Work still to be done

More than 95% of the concrete structural work on the platforms, the two car parks, the staircases and escalators providing access to the station bridge, as well as the complete modernisation of the railway infrastructure excluding the overhead lines, has been completed. Work on the station’s overhead line infrastructure is 85% complete.
Elisa Roux: “Their completion depends, in part or entirely, on the steel frame being finished. The same applies to the façades and roof, as well as the escalators and lifts. These works can only be carried out once the bridge is resting on its permanent supports.” The transfer onto the permanent supports is currently under way. “Once the canopies have been installed, Infrabel will be able to fit the overhead lines,” explains Frédéric Sacré. The remaining work will include assembling and attaching the entrance canopies, completing installation of the roof lanterns, manufacturing, assembling and erecting the canopies and platform shelters, installing the frames and solid or glazed panels, cladding and finishing the platforms, and finally implementing the IT systems for passenger information, including displays and public address.
This means another good year’s work for the companies responsible for the various parts of the project!
Some figures…
Bridge length
240 m (between the ends of the canopies)
Bridge width
33 m
Bridge deck level
7,20 m
5 covered platforms
350 m long and 8,50 m wide
12 lifts and 14 escalators
Internal height
15,80 m
Internal roadway
14,70 m
Total weight of the steel structure
6 500 tonnes
Glazing and roof panels
30 000 m²
Total internal floor area
4 800 m²
Also…
2 700 m² of roadway and waiting areas
+/- 600 m² of offices and services
+/- 1 500 m² of retail space
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectConstruction