Meticulous work for an even better centre of excellence in Charleroi…
Texte Philippe Selke | Photo Pascal Thémans Productions pour Duchêne

On 21 September, the Zénobe Gramme University Centre hosted an exceptional joint academic year opening ceremony for ULB and UMONS. The recent conversion works, included in the 2014-2020 ERDF programme and carried out by the Lixon, Monument, Duchêne joint venture, have created a magnificent, functional space in this historic building, conducive to teaching and student development. A closer look at a construction project like no other, of major importance to Charleroi and an example of sustainability through pooling resources around a shared project that reuses an existing building.

Inaugurated on 28 May 1911, on the eve of the opening of Charleroi’s major industrial and commercial exhibition, the Zénobe Gramme building is now enjoying a new lease of life as one of the key components of the new CampusUCharleroi. It brings together higher and university education, training, scientific research, the communication of scientific knowledge, and awareness-raising about scientific and technical careers. The conversion and restoration work began on 12 November 2020 and was (almost) complete in time for the 2023 academic year. Stabilisation, structural work, specialist building services and finishing works followed one another at a brisk pace. Only the package covering the restoration of the façades, external joinery and cornices is still under way, after being postponed by the client for budgetary reasons.
Emmanuel Franc, Building Director for Hainaut at Duchêne: “Within the joint venture, we divided up the roles to work effectively together, with Lixon managing the project and Duchêne providing the lead site manager. This renovation project involved a substantial amount of restoration, so we needed someone experienced and passionate about restoration. That is why Philippe Soltysik left the Chaufferie site (Ed.: another Duchêne project in Charleroi, which we covered in an earlier issue) to join the Zénobe Gramme project. He led the latter almost to completion, with Youri Kamalic taking over for the rest of the finishing works. Monument’s experience in heritage restoration proved invaluable throughout the project, and they are currently working on the façades.”

Countdown to a building more than a century old
Listed as a historic monument in 2004, the building housed, across nearly 12 000 square metres, grand exhibition halls lit by three large glazed roofs, showcasing the technological expertise of the time, as well as a majestic main hall and numerous teaching spaces. Following its conversion, it has become an exceptional setting for higher and university education, as well as scientific research, and is now home to the “Centre of Excellence in Energy Efficiency and Sustainable Development (C3E2D)”.
The conversion included, among other work carried out by a multidisciplinary team: restoration of the main hall; renovation and restoration of the decorative features, and reconstruction of the glazed roofs in the two main rooms, the Industrial Museum Room and the Machinery Room; restoration of the corridors; redevelopment of the courtyards; renovation of the façades to their original condition; and refurbishment of the interior spaces to accommodate the active learning methods used in today’s education sector.

Martin Monnart, architect-engineer and partner at archipelago, has followed the project from the outset. “We submitted our application in 2018, just 5 years ago. From the start, we had a precise deadline: the beginning of the 2023 academic year. This was further reinforced by the deadline for using the ERDF funding, set at 31 December of the same year. It was an ambitious target: to bring a century-old building, which was in a very poor state, back to life while incorporating all the technology of today, in terms of programming, teaching, research, sustainability and building services…” “
The design challenge was taken on by a duo of architectural practices, Ma2 (Francis Metzger), a renowned heritage restoration specialist, and archipelago, experienced in major projects. “That was in addition to the engineering consultancies, including BESP, which did outstanding work on the structural engineering. The subsoil was criss-crossed by mine galleries and remains of fortifications, and we discovered that the existing building had subsided, with a 60 cm difference in level between its two ends!”

A construction project where everything is interconnected
As Lixon project manager Arnaud Bertouil explains, the first phase of the work, the structural works, lasted about a year. In early 2021, it made way for the next contract, covering finishing works and specialist building services, which kept the teams busy until the building was commissioned. Built in part on brick arches that had been damaged by work carried out nearby in the 1960s and 1970s, the building first had to be stabilised, during a first phase full of surprises. The next stage was just as complicated, although better controlled, and mainly involved creating new technical rooms, some of them beneath the existing structure, a real feat. Major propping was needed to suspend the listed perimeter gallery and allow excavation, after all heritage features, including the terrazzo flooring and staircases, had been removed or protected. Youri Kamalic, site manager at Duchêne: “A huge amount of cataloguing took place before the elements to be preserved were dismantled: tiles, oak doors, brass handrails, blown-glass light fittings… Everything was stored off site so it could be reinstated after restoration, two years later. The finishing works also had to be carried out using methods appropriate to whether the work area was listed or not. That was one of the project’s particular challenges: listed and unlisted areas are closely interwoven. The two types can follow one another along the same corridor…” Equipping the building with modern systems, such as underfloor heating and ventilation, without compromising its historic character was therefore a major challenge. As a result, ventilation ducts are clearly visible in the unlisted lecture rooms and offices, but never in the large forum or circulation areas.

Meticulous and fast-paced
The finishing works also involved several craftspeople specialising in particular aspects of restoration, for example the plasterwork in the large forum. Others worked on the light fittings in the main hall, the building’s principal entrance, which is listed as Exceptional Heritage of Wallonia. Youri Kamalic: “We maximised the amount of concurrent work from May to July 2023, towards the end of the project. “
My job was to coordinate all the trades, who are not necessarily used to working together, for example a lighting restorer and an electrician, so we could meet the deadline. And we managed it because everyone bought into the project and did their part.”
Such meticulous work on a project of this scale (around 20 000 m2) is far from commonplace, and the joint venture carried it out remarkably well, as Arnaud Bertouil confirms: “I do think Duchêne’s site management deserves recognition. They also put a great deal of work into the programme, which was no easy task given the size of the building and the often very different timescales for restoration and new construction, where productivity rates are more predictable in advance.”

Emmanuel Franc: “I have worked on a few restoration projects during my career, and what pleasantly surprised me about this one was how quickly decisions were made. Traditionally, on a project like this, it takes longer. If Zénobe Gramme was ready by the deadline, that was thanks in particular to the energy put in by the project manager, but also by the client, to keep things moving. We couldn’t afford to wait, so we kept chasing the architects and the clients. It wasn’t all plain sailing, but everyone did their bit.”
Speaking on the eve of the inauguration, Martin Monnart confirms: “Projects of this scale, with a major heritage component, generally take 10 years or more. On this one, everyone involved, from AWAP to the contractors, understood what the project meant for Charleroi. It is quite exceptional that this building could be completed in such a short time.” This is an example to follow, as is the way several institutions came together to create a hub combining education and applied research, while reusing an existing building. Zénobe Gramme can be seen as a model, where a substantial amount of embodied energy was saved through a strong dose of collective intelligence.”
Duchêne never really leaves Charleroi: as soon as its Zénobe Gramme project ends, work begins on the extension of the Charleroi metro… more in a future issue of Construire la Wallonie.

Question about this story? Ask your question
Who worked on it
- Clientasbl Centre Universitaire Zénobe Gramme (Province du Hainaut, ULB, UMONS, Ville de Charleroi/Université Ouverte)
- ArchitectsMa²-Francis Metzger et archipelago
- Main contractorSM Lixon: Monument: Duchêne
Keep following this
Get an email when a new story is published. No account needed.
- SubjectConstruction