Local expertise brings strength to the Liège Expo roof
Texte Philipe Selke Photos S.A. Vincent Piront

While the architects’ initial visualisations showed a complex worthy of a spacecraft from Star Wars, economic realities soon brought everyone back down to earth. Against this backdrop, adapting the roof without changing the building’s usable floor area proved decisive. S.A. Vincent Piront, in a temporary joint venture with S.A. HD Systems, only worked on the adapted version of the project, which featured extensive roof areas that were easier to tackle than the geometry originally proposed. S.A. Vincent Piront drew on its expertise and capacity to deliver the building’s thermal and acoustic insulation, as well as waterproofing for its 17 000 m2 of roof, in just 170 calendar days!

Verviers-based S.A. HD Systems, a company specialising in metal roofing, handled all the building’s cladding, as well as the steel decking supporting the roof. S.A. Vincent Piront installed the insulation and waterproofing build-up above it, including a Phonotech acoustic insulation layer covering more than 12 000 m2. This acoustic insulation limits noise breakout from certain halls in the building. In addition, to meet fire safety standards, around 40 smoke vents were installed on the two slopes of the central section.

Professional work
And it was far from an easy job. Aldrin Bytyqi, site manager and project manager, explains: “The 17 000 m2 to be completed were divided into 7 different build-ups. The specific uses of each area of the building meant that each required a different treatment. Acoustic attenuation was, of course, our biggest challenge.”
The safety of the workers on site was taken very seriously. “HD Systems had included a sacrificial fixing at the head of each sandwich panel, to which we could attach the temporary guardrails. Thanks to this very specific system, our teams were able to work in complete safety until the waterproofing and the finishing capping were installed. Once the work is complete, we remove this edge protection using a MEWP. It can easily be reinstalled if further work is needed.”

Fast and effective
With projects such as the LOSC Stadium in Lille, Paris La Défense Arena and the Le Centre Orléans Métropole CO’Met, all three also fitted with acoustic insulation, S.A. Vincent Piront is accustomed to large-scale projects requiring both expertise and the capacity to deliver. Drawing on experience gained across its projects, the Liège-based company is one of the few capable of delivering impeccable work that incorporates the specific requirements of acoustic insulation, often to very tight deadlines.

Vincent Piront: “dB, frequency, noise breakout, vibration transmission… these are concepts we know well. This specialism enables us to work directly with the acousticians on projects.” Aldrin Bytyqi adds: “We had been allocated 270 calendar days to complete this project. Due to the overall project schedule, the client asked us to finish our work in… just 170 days. We rose to the challenge by significantly increasing the size of our teams, despite particularly wet winter weather.”
As work progressed, S.A. Vincent Piront handed over one area after another, allowing work to begin inside the building. Needless to say, given the result, the client could only be satisfied!
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectConstruction


















