Hissého, a fine project rises above the water
Texte Philippe Selke Photos Lauriane Genart pour Duchêne

Opened at the end of August 2024, the new swimming pool is a relief for the people of Courcelles, who had been waiting for it since the old one closed in 2016. For the mayor and her alderman for sport, it marks the culmination of a very long journey beset by political, planning and even… weather-related obstacles. But the result is here, a brick-coloured monolith with an azure-blue heart. General contractor Duchêne, working on a design and build basis with architects Réservoir A and engineers GEI, made a major contribution to bringing this project to the surface.
The municipality initially considered renovating the existing swimming pool, but it soon became clear that the cost of bringing it up to standard would be far too high. A competition was therefore launched to build a new pool, and the contract was awarded to the Duchêne, Réservoir A, GEI consortium.
The original plan was for the building to be clad entirely in metal, for budgetary reasons. However, obtaining planning permission meant replacing the metal sheeting with brick. And that was not all. Julie Schoonyans, Site Manager at Duchêne: “When the permit was granted, we found that we had to add electric vehicle charging points and install ballasted photovoltaic panels across the entire roof, which meant revisiting all our structural calculations.”

Under water from the outset
Once work began in October 2022, an unforeseen constraint had a major impact on the progress of the project: “From the very start, the weather set us back by several months. It was extremely difficult, with all the main phases of the structural work affected, including the building’s roof, which was repeatedly delayed.”
Green Acess-i label
A major challenge for the designers and contractor was to ensure that anyone with reduced mobility or any kind of disability could get from their car to the bathing area and swim without any assistance from another person. This is the highest level of accessibility, recognised by the green Acess-i label.
Julie Schoonyans concludes: “Being in the same boat from the design stage enabled us to overcome the constraints and meet the challenges. Everyone had to make compromises so that we could succeed together.” With another pool renovation and extension project under way in parallel in Farciennes, Duchêne has added two fine projects to its portfolio of references.
Question about this story? Ask your question
Who worked on it
- ClientCommune de Courcelles
- ArchitectRéservoir A
- Structural and building services engineerGEI
- General contractorDuchêne (Groupe Eiffage)