Innovating in renovation

Texte Philippe Selke Photos Six Consulting & Engineering

350 panneaux photovoltaïques totalisant 153 kWc généreront une autoproduction photovoltaïque attendue de près de 80 000 kW/an.
350 panneaux photovoltaïques totalisant 153 kWc généreront une autoproduction photovoltaïque attendue de près de 80 000 kW/an.

For engineering consultancy Six Consulting & Engineering, the Solidaris project in Charleroi has a particular significance: it is a major renovation, whereas the consultancy had until then been mainly active in new-build construction. The project’s success opens up new prospects for Gérald Maljean and his team.

From the design stage, the focus was on the energy concept, with priority given to the building envelope to achieve a K25 rating. The consultancy then concentrated on innovative, rational building services to achieve outstanding performance (Ew 38 against a recalculated required value of Ew 67). These measures made it possible to cut electricity and heating consumption by more than 40% compared with the legally required levels, generating estimated savings of more than 400 000 kWh/year and expected photovoltaic self-generation of nearly 80 000 kW/year.

The entire building is heated and cooled by a 150 kW reversible air-to-water heat pump. A gas boiler and a chilled-water unit provide additional capacity to meet demand. This system, combined with 350 photovoltaic panels with a total capacity of 153 kWp, makes the building highly energy-efficient, with maximum self-consumption.

A correctly sized air handling unit contributes to the comfort of employees and visitors.

The electrical renovation was also extensive, from the client’s high-voltage substation to the end user’s socket. In addition, the open-plan floors and versatile spaces called for highly precise lighting and equipment-positioning studies. 

Fire safety was also a major consideration for the building. The car parks were renovated to bring them up to current standards. A comprehensive sprinkler system had to be integrated throughout the car parks, despite significant headroom constraints. 

Gérald Maljean concludes: « Renovation work comes with its fair share of surprises and constraints. We had to work around existing service ducts and plant rooms to integrate our new systems, while complying with the requirements of the Code on Well-being at Work. Our teams’ expertise and know-how, together with the use of 3D modelling software, enabled us to anticipate conflicts with the existing building as far as possible. It was a major challenge, but the result is a success in every respect, thanks to the excellent collaboration between all the design teams, site teams and the client. It has also enabled Six Consulting & Engineering to develop new skills and gain a magnificent reference project in major renovation. »  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeRenovating existing buildings
  • SubjectHainaut
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.