Extensive surroundings delivered through a short supply chain
Texte Philipe Selke Photo Urbanisme – Ville de Liège

Based on the banks of the Meuse in Wandre (Liège), roadworks specialist AB Tech (Groupe Joly) took sole responsibility for package 7 of the Liège Expo project: the exhibitor and visitor car parks, the esplanade, water-retention areas and infrastructure adjoining the tramway. From September 2022 to June 2024, it brought all its expertise to bear on what is now one of its biggest projects, with sustainability a key priority!
The main challenge was the scale of the project and meeting tight deadlines. An average of 15 workers were on site, with numbers peaking at 35. The following figures give an idea of the scale of the works: 37 500 m2 of surfacing in total, including around 12 000 m2 for the visitor car park and 9000 m2 for the exhibitor car park, laid with grass pavers; 8700 m2 of two-layer asphalt; 8000 m2 of grey exposed-aggregate concrete on the esplanade; and finally 11 500 m2 of pervious asphalt in the logistics area. Before work began, the soil was treated with lime to give it the required load-bearing capacity. 13 000 m3 of earth was moved, with cut and fill balanced so that all the material remained on site. The works then used 30 000 tonnes of stone from the Bloquay sandstone quarry, owned by Groupe Joly, as well as 3000 tonnes of recycled 0/63 aggregate from the Terranova sorting centre on Monsin Island. The Liège Expo project therefore made use of local resources, both in terms of labour and materials.
Blue and green
Bernard Grzesinski is the site manager: “The aim here was to allow rainwater to infiltrate the ground rather than send it into the sewer network and overload it, in full compliance with the Water Code of the Walloon Region. Runoff water passes through retention basins and then oil separators before being released into the ground via the numerous swales. This protects the groundwater in the close-in catchment area, given the nearby presence of the AB Inbev brewery. Producing and placing so much aggregate in the basins was a major challenge, as the quarry and the logistics had to keep pace.”
The icing on the cake is that, where the surroundings of exhibition halls are too often entirely mineral, Liège Expo will make room for plenty of greenery, with no fewer than 300 trees and 40 000 plants to be planted, as well as grass pavers in the car parks.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectConstruction