Electrifying working environment for TEC bus maintenance and repairs

A bus maintenance and repair workshop does not have to be a dull, uncomfortable place. That, at least, was the vision of the Opérateur de Transport de Wallonie (OTW) when it commissioned Atelier de l’Arbre d’Or to design a new workshop for TEC Namur-Luxembourg. Built on the site of the Malonne bus depot, the facility helps workers identify with their employer and promotes their wellbeing at work.
With the ongoing transition to hybrid and electric buses, changes to energy performance requirements and occupational safety standards, the old workshop no longer met current or future needs.
Around 60 metres long and 24 metres wide, the new building comprises nine bays: three have maintenance pits, four are fitted with vehicle lifts, and two house staff facilities and equipment storage. Seven sectional doors punctuate the façade, each topped by a large polycarbonate panel to bring as much natural light as possible into the building. A canopy runs along the façade to prevent overheating. It is yellow, a nod to the TEC logo.

Safety and wellbeing
As the workshop is close to the depot, where buses are constantly entering and leaving, and buses require considerable space to manoeuvre, the hall was designed with through access, allowing buses to enter at one end and leave at the other. This ensures the smoothest possible traffic flow around the site and helps prevent accidents. Each sectional door also closes automatically and quickly once a bus has passed through, saving energy and ensuring workers’ thermal comfort.
Cédric Poncelet, Associate Architect at Atelier de l’Arbre d’Or: “We sought to bring together the client’s technical requirements, energy needs, since the building is in constant use, and the wellbeing of the people working there.”
A conventional construction method, with an added benefit
Construction of the new workshop by Bemat-Moury was completed in summer 2021. It involved significant work to build a series of galleries beneath the building. The above-ground structure uses a precast reinforced-concrete column-and-beam system. The façades have concrete plinths for maximum strength, topped by metal sandwich panels. The roof, also made of metal sandwich panels, is designed to accommodate photovoltaic panels. A huge rooflight brings in even more natural light for the workers.
The pedestrian entrance is on a side façade. The ground floor houses technical rooms for tyre storage and a parts store. The first floor contains changing rooms with showers, a staff room with a kitchenette, and a meeting room. Given its south-facing orientation, the meeting room is also protected from overheating by a canopy.
Cédric Poncelet: “It may not look like much, but we still faced some significant challenges in terms of stability, with beams 40 m long, and coordination between architecture, structural engineering and highly specialised building services, such as oil distribution points and exhaust extraction, to ensure everything was perfectly integrated.”

An investment in the future
As we write, the interior equipment, procured under a separate contract package, has just been installed. Given the constant evolution of technology, this is an investment in the future. Hybrid buses require different maintenance and repair procedures from conventional internal-combustion-engine buses. As for the external works, which form a third contract package, the workers are presumably eagerly awaiting their completion so they can take up their new workplace…
Question about this story? Ask your question
Who worked on it
- ClientOpérateur de Transport de Wallonie (OTW)
- ArchitectAtelier de l’Arbre d’Or
- Main contractorBemat-Moury