E42/A8 towards France: Roundabout to be built at exit 35 “Blandain/Hertain”

Work to build a roundabout at exit 35 “Blandain/Hertain” on the E42/A8 towards France will begin on Monday 16 September.
Work on a roundabout at exit 35 “Blandain/Hertain” on the E42/A8 towards France will begin on Monday 16 September.
Specifically, the project will:
- create a new roundabout providing access to the new Tournai Ouest III business park, developed by the IDETA Territorial Development Agency;
- resurface the N7 between the roundabout and the N7/Route de Blandain junction;
- adapt the exit slip road at exit 35 “Blandain/Hertain” towards the N7.
Traffic conditions and impact
For the duration of the works, the N7 will be closed in both directions between the junction with Route de Blandain and Chemin du Faisan.
- A diversion will be in place in both directions via Chemin du Faisan and Rue René Lefebvre.
As a result of this closure, traffic coming from the N7 will no longer be able to access the E42/A8 towards France directly.
- A diversion will be in place via the Marquain interchange.
The exit slip road at exit 35 “Blandain/Hertain” on the E42/A8 towards France will remain open during the works, except for two weekends towards the end of the project (the dates will be announced later), when the new roundabout will be connected to the existing slip road.
- A diversion will then be in place via the Marquain interchange.
The project has a budget of €1,895,036.93 excluding VAT, of which:
- €714,370.82 excluding VAT will be funded by SOFICO
- €1,180,666.11 excluding VAT will be funded by IDETA under a funding agreement through a Marshall Plan grant
The works are due to be completed by the end of May 2020.
The works will be carried out in collaboration with SOFICO’s technical partner, the Walloon Public Service for Mobility and Infrastructure.
Tournai Ouest III business park is an important project for the economic future of Picardy Wallonia. It will help ease the capacity constraints at Tournai Ouest I and II and provide serviced plots for businesses wishing to invest in the region. IDETA is currently completing the first phase of the business park’s development, covering almost 25 hectares of new plots.
The new roundabout and a direct road link will ease congestion at the existing access points and improve mobility within the Tournai Ouest business area.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectConstruction