Constructive dialogue and flexibility for essential forward planning
Texte Philippe Selke Photo CEGELEC

Benoit Gouverneur, Business Development Manager at Vinci Énergies: Building Solutions Belgium: “Our CEGELEC business was responsible for the HVAC and plumbing package, in a 50-50 partnership with VMA, with each company working in a designated area of the building (blocks A, B and C for CEGELEC). As the tenants were not yet known during the works, we had to anticipate their needs by building as much flexibility as possible into the installations, for both the offices and the laboratories.”
The main challenges on this project were bringing the energy-generation systems into operation ahead of schedule (as block D was due to be handed over by June 2025), working alongside other trades and meeting very tight deadlines for a building of this size.
The installed equipment delivers high energy efficiency (air handling units with a rotary absorption wheel for the offices and air handling units with heat recovery coils for the laboratories) and considerable flexibility (variable water and air flow rates). The office floors are cooled by active chilled ceilings with self-regulating 6-way valves, while metering systems enable detailed energy monitoring by floor and tenant. A BIM model has been delivered to the client, Igretec, for operational and maintenance purposes.
Benoit Gouverneur concludes: “None of this would have been possible without flexible, constructive collaboration between our experienced teams and those at VMA, on the one hand, and with Igretec’s teams, on the other, paving the way for the search for optimal solutions.”
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- SubjectConstruction