An unusual, fast-moving project delivered with method and creativity
Texte Philippe Selke Photos Yvan Glavie, Dherte & Pairi Daiza

A management team of around 15 people, up to 400 people working on site at the same time, concrete pours across 8 different levels beneath a glass roof, dozens of small projects within the main project, … building the world’s largest tropical greenhouse called for intensive preparation, constant commitment and close coordination between the many parties involved. The temporary joint venture SM Dherte, CIT Blaton, BPC Group rose to the challenge. Here is a look back at a uniquely complex three-year project.
Initially, the contract awarded to the temporary joint venture between the three main contractors covered all the structural work, including hotel rooms, some of them underwater or built into the cliffs; guest facilities (restaurants, terraces, lobby and public areas); technical rooms for plant and animal care; pools for various species (sharks, manatees, etc.) and a river running through the site; as well as numerous underground structures and the perimeter wall supporting the greenhouse.
Partway through the project, the joint venture was also tasked with coordinating the specialist building services and fit-out packages. Some specific packages and finishes (such as earthworks, planting, pool waterproofing, artificial rockwork and enclosure landscaping, etc.) remained under the direct responsibility of the Park, with the trades coordinated by Jérémy Lannoy, Pairi Daiza’s Director of Major Projects, and his teams. This dual coordination led to intensive discussions, particularly around releasing work areas and managing access for the final fit-out (bedding, lighting, etc.).

Method and creativity
The glass roof was installed first, in 2500 m² sections (50×50 m grids), allowing work to progress inside without having to wait for the entire roof to be completed. Christophe Cardinael, CEO of Dherte, a long-standing partner of the Park, said: « We could not afford to wait until the glass roof was fully installed before starting work. Grid by grid, we moved into the area to build the foundations and lower landscape features, until the entire surface was available. »
The approximately 20-metre clear height and the project’s « lasagne » layering, with up to 8 different levels, meant using mobile cranes with limited reach, which are slower than tower cranes and required careful planning. Managing plant movements around the construction site became increasingly complex as the greenhouse’s 4 hectares took shape: stabilising access routes, avoiding fragile areas such as pools that had already been cast and certain planted areas, managing simultaneous operations, … Cédric Vande Moortele (BPC Group), project manager for the joint venture, said: « A colleague from our Methods and Planning department worked alongside our site teams every day to manage this organisational and logistical complexity. Good management of access routes and storage areas was crucial. Temporary ramps were built and removed daily to allow plant to move around and deliveries to be made, right up to the final week of the project. The success of this set-up obviously depended on the full cooperation of the teams, which we had. »


Organic forms make for a dynamic project
Éric Doff-Sotta, CEO of CIT Blaton, who had already worked on a Pairi Daiza project after « Terre du froid », said: « The Edenya project is highly complex, particularly because of the natural forms that had to be recreated. Many structures, such as the caves, are unconventional, requiring bespoke formwork and reinforcement designs devised by the site managers themselves and then approved by the engineers. » The non-orthogonal, non-repetitive forms also limited the use of prefabrication, particularly in areas visible to the public. Indeed, the project includes a « hidden » area almost as large as the visible area, with extensive technical installations for animal care, air conditioning, ventilation and water management.
The project was dynamic because it was constantly evolving, with frequent design changes that required the teams to respond quickly and remain flexible. Daily coordination with the Park and the other parties involved made it possible to adjust schedules and avoid bottlenecks.

A success built on people
This technical and organisational complexity was a real challenge, but also a source of motivation and pride for the teams, including managers, tradespeople and plant operators, who showed ingenuity, collaboration and professionalism to deliver this landmark project.
For this extraordinary project in the truest sense of the word, the three companies pooled their resources, both physical and human, ensuring the teams had complementary skill sets to support commitment and success. « The collaboration worked well, growing even stronger during the more difficult moments until we became like a family », concludes Christophe Cardinael.

Een zakelijke vraag aan BPC Group SA? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectConstruction
- CompanyBPC Group SA