Ampsin-Neuville: installation of the new lock gates completed successfully!

On 13, 14 and 15 May, a symbolic and impressive milestone was reached in the construction of the new large-capacity lock (225 x 25 metres, capacity of 9,000 tonnes) at the Ampsin-Neuville site: the gates for the new infrastructure were delivered to the site. Take a look at the operation in pictures!
To allow boats to enter and leave, the lock is fitted with a flap gate and a mitre gate.

FLAP GATE
The flap gate is located at the upstream end of the lock. It is a structure consisting of a stiffened steel panel weighing more than 90 tonnes, approximately 30m long and 6m high. The panel is hinged at its base and pivots around a horizontal axis. It lies flat on the bed of the lock to allow boats to pass over it. Once boats have entered the lock, the flap gate is raised by rotating it with two hydraulic cylinders.

MITRE GATE
The mitre gate is located at the downstream end of the lock. It consists of two leaves, each weighing more than 100 tonnes and pivoting around a vertical axis. To withstand the water pressure caused by the difference in water levels created by the barrage, the two leaves bear against each other at the centreline of the lock. Each leaf is approximately 10m high and 14m wide.
The downstream mitre gate is taller than the flap gate. Its height is determined by the draught of boats in the downstream pound and by the head created by the barrage. The height of the upstream gate is determined solely by the draught of boats in the upstream pound.
Both gates were transported by boat from the manufacturer's workshops.
Question about this story? Ask your question
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectConstruction