Passage sous voies, station de relevage, réfection des voiries jusqu’au coffre, pose de gradins, … le chantier combinait des travaux différents demandant chacun une expertise spécifique.
Passage sous voies, station de relevage, réfection des voiries jusqu’au coffre, pose de gradins, … le chantier combinait des travaux différents demandant chacun une expertise spécifique.

In recent months, Construire la Wallonie has reported on projects showcasing the intelligent diversification pursued by sprimont-based company eloy: demolition, recycling and treatment of construction ‘waste’, property development and building construction for third parties, development of business parks, … It is easy to almost forget eloy’s historic core business: infrastructure works. Combining several challenges, the project at the ‘Chêne Madame’ junction in Neupré is a remarkable example of eloy’s expertise in this field.

Given the high volume of traffic on this route, traffic management was one of the biggest challenges, with strict phasing to minimise the impact on road users.

The Rotheux junction, known as the Chêne Madame junction, on the busy Route du Condroz in Neupré, was known as a particularly accident-prone spot. The Walloon Region (SPW) therefore launched a major safety project, involving the construction of two junctions with intelligent traffic lights and a cycle and pedestrian tunnel beneath the road, complemented by a car-sharing car park. The entire project was entrusted to eloy, with the task of completing it within 14 calendar months while following a phasing plan designed to keep traffic moving and maintain activity in the surrounding area.

“I don’t think we have ever built such a substantial underpass before.”

A project drawing on a wide range of skills

A 6 to 8 m-wide underpass with an access ramp, a pumping station, road resurfacing down to the formation, steps installed as street furniture, … the project brought together different types of work, each requiring specific expertise. John Gillard, Site Manager at eloy: “I don’t think we have ever built such a substantial underpass before. What’s more, bureau greisch widened and heightened the tunnel entrance on the ramp side to prevent users from feeling hemmed in, which made the formwork and steel fixing more complex. For example, the reinforcement for the base slab, walls and roof slab all had to be made to measure… Fortunately, we had both a roads site manager and a site manager with a stronger background in building and civil engineering, and expertise in formwork and steel fixing. I specialise more in infrastructure myself, but also have experience in building construction. One of eloy’s strengths is its ability to bring the right skills to bear in the right places, enabling it to deliver a project with as many different facets as this one.”

eloy’s own workforce was on site, with a team leader and machine operators present at all times. Some specialist tasks, such as asphalt laying, were subcontracted to specialist companies.

Despite the constraints and unforeseen issues, eloy’s teams managed to organise their work so as to limit the delay to around one month, which is quite an achievement.

Numerous significant constraints

John Gillard: “The main constraints we encountered were the poor ground conditions, traffic management and, of course, the weather. Since work began in August 2023, it has done
little but rain…” ∂ 

For example, because of the marshy ground, eloy had to shore up certain excavations to ensure safe working conditions. It also had to deal with larger-than-expected volumes of soil to be removed, requiring further analyses and Walterre certificates. “Twice we ran into this problem, which meant storing the soil on site while we waited for the certificate. Each time, we had to wait 3 to 4 weeks.” 

Unexpected encounters with certain underground utilities also caused minor delays. A directional bore for the installation of a new 220 kV underground electricity connection for Elia, although known about, added a further constraint during work on the pumping station and tunnel.

Widened and heightened, the tunnel entrance on the ramp side required the use of made-to-measure reinforcement.

Given the high volume of traffic on this route, traffic management was one of the biggest challenges, with strict phasing to minimise the impact on road users. “We made a few changes to the imposed schedule, bringing some work, such as building the ramp and steps, into phase 2 in an effort to limit the impact on local businesses.”

Despite these constraints and unforeseen issues, eloy’s teams managed to organise their work so as to limit the delay to around one month, which is quite an achievement. Collaboration between the various stakeholders, including the client and the local authority, was effective, making it easier to manage expectations. 

Let’s hope a spell of suitable weather in early December allows the surface course to be laid. Local residents, motorists and cyclists will then be able to enjoy a lovely Christmas present at the foot of the preserved Chêne Madame! Especially as eloy is also completing the link between Neupré and the RAVeL nearby.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.