Having already made its mark at Pairi Daiza with its contribution to the Park’s new entrance and, above all, the construction of a restaurant for the Land of Cold designed to resemble a timber church, the company led by Bruno Bodeveix had more than proved its worth. It is no surprise, then, that the Park entrusted it with the construction of almost all the timber frames and structures for Edenya, with only a few boards excepted. It was an exceptionally intense project, carried out under glass over 16 months, as Bruno Bodeveix, director of Charpente & Construction Bois, explains.
Since 2022, the SME based in Braine-le-Château had been supporting Pairi Daiza in research into the technical and aesthetic design of timber structures for the Edenya greenhouse. Charpente & Construction Bois went on to provide a full service, from design studies and 2D drawings, 3D models and design work through to on-site construction, across various areas of the greenhouse: timber frames, walls and cladding for the Rainforest stilt houses (8 rooms), with terraces, balustrades and access walkways; timber frames, cladding for concrete walls, terraces and balconies for the 10 rooms in the Riverine area, as well as the timber frame and structure for the shop and lift shaft, the latter clad in padouk; exposed timber frames for the Beach area’s reception and sales shop, restaurant and bar; French-style ceilings, exposed beams and columns in the 10 underwater rooms; the exposed timber frame for the shop at the East entrance, and the ipé structure for all the greenhouse’s fixed bridges, including the longest, which measures 49 m and was built entirely by Charpente & Construction Bois, complete with decking, handrail and gate. There is too much to describe in full in this article, given the number and variety of the works…
Bruno Bodeveix explains: “We started work under the glass roof on 9 July 2024. By 28 January 2026, we had completed our work, right on schedule, including additional requests. It is worth noting that the Park asked us on 20 December to build the Rainforest and Riverine food and beverage outlets. We were on site and ready to start on 24 December. Once that work was done, we received another request, this time for a 170 m² logistics canopy, with an exposed Douglas fir structure and sheet-metal roofing. We completed it in 10 days. During the final week before Edenya opened, we took care of a few finishing details for the Park. That brought 16 months of work to an end, as part of a project lasting 4 years in total, which involved most of our teams, including 19 skilled carpenters, a manager from our design office and a site coordinator.”

Durable structures
Despite the protection provided by the greenhouse, Charpente & Construction Bois designed the structures as if they were being built outdoors. This included the Rainforest stilt houses, which are very slender and up to 11 m high, with galvanised St Andrew’s crosses for stability. The houses are also designed to be fully watertight, with several layers beneath the thatch. The materials used are fire- and insect-resistant and comply with CE standards. The tropical hardwoods (ipé, jatoba, azobé, …), certified as sustainably sourced, were supplied by the Park, while Charpente & Construction Bois supplied the local species. These were treated in an autoclave to Class 4.


A project under glass
Sheltered from the weather, the site was not always a paradise. Bruno Bodeveix says: “As the soil dried out, it quickly turned to dust. The heat could be oppressive at times, as could the noise from the machinery used by the many trades working on site simultaneously. The workers did get used to these conditions, which were all the more unusual because they had to endure them for 16 months, whatever the season. There were no lulls or winter breaks: the work had to carry on. The pace therefore remained intense throughout the project, which is never the case when working outdoors.”


Coordination on all fronts
The work carried out by Charpente & Construction Bois on the accommodation units typically followed the same sequence: building the exposed internal timber frames, installing vapour-control membranes, running the services (electrical, HVAC, plumbing and sprinkler systems), validating the tests (pressure testing), then installing the insulation, waterproofing and battens for the roof covering. Bruno Bodeveix says: “The main contractor managed coordination very well, but we were in charge of our own work, working closely with the Park and the other contractors, such as the earthworks contractor. For example, we provided the elevation points and coordinates ourselves to set out the stilt houses. From October 2024, our teams worked in parallel across Riverine, Beach and Rainforest. Towards the end of the project, when it came to building the 49-metre-long bridge and then the two additional food outlets, the only way to get around the greenhouse was by trolley, starting from a single access point.”

Back down to earth
After being so deeply involved in such a long and intense project, Bruno Bodeveix admits that it was difficult to get back to normal: “When you build for Pairi Daiza, you are so focused all the time that little else matters. You are completely absorbed in the day-to-day work on a site that, sheltered from the weather, carries on without interruption at a constant pace. It can be very hard to get back to your usual activities! After 40 years in the industry, I would say this project stood out for the total commitment of the company, the strong synergy with the Park and the other contractors, and the recognition of our craftspeople’s efforts.”
Millions of visitors will have the opportunity to admire the work of Charpente & Construction Bois, which, unlike that of other companies, is highly visible. As soon as you enter the greenhouse, the timber proudly takes on a distinctive aesthetic role, blending seamlessly with the tropical vegetation.