A new water tower built entirely from concrete

The Belgian landscape is dotted with water towers of every type and size. Feluy, in Hainaut, is no exception, with a new structure recently becoming a landmark there.
The municipality of Feluy had a clear need for this new construction to replace the existing metal water tower and meet growing demand from businesses in the local industrial zone, Belgium’s second petrochemical hub after the port of Antwerp. Petrochemical production processes require considerable volumes of water, supplied by the intermunicipal utility IDEA.
However, the existing metal water tower had not been designed to withstand the chlorine used to disinfect the water. Stability problems had also been identified at the floor slab anchorage. Galère therefore proposed building the new water tower entirely from concrete.

The new structure stands 56.4 m tall and has a storage capacity of 2500 m³ of drinking water.
When constructing this impressive structure, it was important to achieve a uniform, watertight surface with no connections or joints, ensuring the construction would be durable and the water tower could be brought into service relatively quickly. Quite a challenge! With its concrete admixtures, concrete repair and protection solutions, and flooring solutions, BASF, Master Builders Solutions’ extensive range for the construction sector was ideally suited to meeting these requirements.
BASF admixtures to control concrete setting
To build the water tower without connections or joints, Galère proposed using slipform shuttering. This solution also helped speed up construction. However, for slipform shuttering to be successful, the concrete mix had to meet specific requirements. The setting time also needed to be known in order to calculate the construction rate. This is determined in particular by the quality of the concrete, the temperature and the admixtures used.

To delay the setting of the concrete so that it could be worked for 7 to 9 hours, the company used MasterSet R 130, a set retarder. For the pillars, it used MasterGlenium SKY 576, a high-range water-reducing superplasticiser specially designed for concrete to be transported. For the floor slab and reservoir walls, it used MasterGlenium SKY 593, an admixture suitable for use in concrete intended to come into contact with drinking water.
The MasterGlenium range was specifically designed for structures that require a certain degree of workability to be maintained, high early strength and a long service life. Workability retention, high durability and compressive strength were all crucial to building this water tower.
Long-lasting protection with MasterSeal, for a long service life
To provide lasting protection for the concrete and reduce the risk of potential failure, it was coated with MasterSeal 550, a flexible, watertight coating based on a hydraulic binder that slows carbonation and can be applied to new concrete exposed to both positive and negative water pressure.
The new water tower in Feluy not only enhances its surroundings, but also ensures a lasting and sufficient water supply for one of the region’s most important economic activities.