A major deep foundations project

Une paroi de 746 pieux sécants de diamètre 63 cm a été réalisée sur une profondeur d’environ 12 m (dont au moins 0,50 m foré dans la roche).
Une paroi de 746 pieux sécants de diamètre 63 cm a été réalisée sur une profondeur d’environ 12 m (dont au moins 0,50 m foré dans la roche).

In central Namur, Thomas & Piron entrusted specialist contractor Soetaert with the deep foundation works for the Novia project. A major undertaking given the groundwater, the size and depth of the excavation, and the completion deadline.

In autumn 2020, a construction excavation covering approximately 9,000 m², with two excavation levels and a perimeter of 415 m, was created using 746 secant piles, each 63 cm in diameter and approximately 12 m deep (with at least 0.50 m drilled into the rock). The wall thus formed was reinforced with two rows of ground anchors to support the two levels of underground parking.

Given the site’s proximity to the Meuse, keeping the excavation dry required large-scale groundwater drawdown, with 6 pumping wells drilled and kept in operation for practically the entire structural works phase. 

Soetaert deployed three piling rigs to meet the completion deadline.

Once the required excavation level had been reached by the earthworks contractor, Soetaert then drilled 301 micropiles to anchor the raft against water pressure during the final phase. The drawdown could not be stopped and the anchors could not be destressed until the structural works had reached their third level. It was therefore a long-running project, with Soetaert’s work finishing in spring 2022.

Isabelle Glorieux, technical sales manager at Soetaert: « This was a major project in terms of both scale and duration. We deployed three piling rigs to meet the completion deadline. As for the drawdown, enormous flow rates were needed to pump the water out. 5 of the 6 pumps were only taken out of service a few weeks ago. Although we generally carry out the earthworks ourselves, here we had to work with the earthworks contractor. Everything went smoothly despite the COVID-19 pandemic. The project had been well prepared and was very well organised. »  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.