A construction site at the centre of everyone’s attention

Texte Philippe Selke Photos Nonet

Un savant phasage du chantier a permis à cette partie de la ville de continuer à fonctionner pendant les travaux.
Un savant phasage du chantier a permis à cette partie de la ville de continuer à fonctionner pendant les travaux.

The Walloon capital is being transformed by numerous construction projects, the main ones having already been covered in these pages. Place de la Station and Boulevard Ernest Mélot carry considerable flows of pedestrians and vehicles at peak times. This major Namur thoroughfare has therefore been completely redeveloped to make it calmer and more welcoming. Nonet was responsible for the works, funded by the City of Namur and SOFICO. A construction project that set an example for efficiency… but which was still unfinished as we went to press, owing to a disagreement over the specifications of the paving stones to be laid.

The surface works were preceded by the installation of new sewers and duct networks with inspection chambers for utilities.

Nonet was tasked with the complete, in-depth renewal of the surfaces in Place de la Station and on Boulevard Mélot, widening the pavements with natural sandstone paving (supplied by Nijst) to give pedestrians more space. This involved removing the central island in front of the station. The new road surfaces were specified in coloured exposed aggregate concrete (TSBV) and asphalt (Willemen). The surface works were preceded by the construction of new sewers and the installation of duct networks with inspection chambers for utilities. New signage, planting, road markings and CCTV cameras complete the project. Three teams from Nonet’s roadworks division were deployed from 13 March 2023 to carry out demolition, sewer works, the installation of linear elements in bluestone and concrete, and the sub-base and foundations for the roads and pavements.

Impasse des Ursulines was not forgotten.

A complex construction site

Project manager Olivier Nulens oversaw the technical, financial and administrative management of this emblematic but complex project. He highlights some of the constraints, starting with the management of existing utilities. “It was a real tangle of cables and pipes, whose exact positions were not always known to the various utility operators. What is more, we came across reinforced-concrete structures of all sizes and undocumented culverts, some of which stood higher than the finished level specified in the project! This made scheduling much more complicated and required us to react at all times.”

Ensuring the impressive flows of pedestrians could move safely around the site was no easy task either. Careful phasing of the works allowed this part of the city to keep functioning throughout the project. “We had to keep a traffic route open at all times between the station and Rue Godefroid, as well as a route around the perimeter so people could walk alongside the buildings on both sides of Boulevard Mélot. Fortunately, everything went smoothly. I would also like to thank the taxis, TEC, SNCB, the police, SPW and the City of Namur for their excellent cooperation!” 

Now calmer, Boulevard Mélot will soon come back to life.

A stone in the pond

On 22 December 2023, 2 months ahead of the deadline, the works were complete, apart from paving the pavements with 15×15 sandstone setts and the finishing work that depended on it. This finishing work includes installing street furniture and lighting columns, as well as fitting the cameras, all of which require anchoring in the ground. Olivier Nulens: “We put all our energy and efficiency into delivering this project, including working through leave and weekends. Located at the heart of our region, it is a highly visible landmark. Despite this, instead of earning praise for finishing ahead of schedule, we risk being fined for delay… The SPW Quality Unit is applying the Qualiroutes approval procedure for sandstone setts with zealous rigour. These setts naturally have a unique face, which means each one differs very slightly from the others. A matter of millimetres…” 

Having the courage to opt for a natural material from our Walloon quarries, as the City of Namur did, can therefore complicate the completion of a project, even in the capital of Wallonia. We hope, however, that this will soon be resolved, so pedestrians can be spared the obstacle course they currently face around the station. 

Indeed, Nonet has already used sawn reclaimed setts of this kind on other projects in the capital, notably on the Esplanade de la Confluence and at the Citadelle, to everyone’s satisfaction. Nonet has also recently won two new contracts to continue linking the lower and upper parts of the city, as part of the extension of Namur’s pedestrian zone.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.