Construction

620 km of cables for the world’s largest tropical greenhouse!

Texte Philippe Selke Photos Arno Louwagie

Pour la détection incendie, une solution par aspiration a été mise en place, avec près de 4,6 kilomètres de tubes capables d’analyser l’air en continu.
Pour la détection incendie, une solution par aspiration a été mise en place, avec près de 4,6 kilomètres de tubes capables d’analyser l’air en continu.

Electrically equipping the world’s largest tropical greenhouse was no ordinary project. For the teams at Collignon (a subsidiary of Eiffage Énergie Systèmes, Belux), the main challenge was adapting to a project that was constantly evolving, with technical solutions needing continuous adjustment to reflect the architects’ creative ideas.

Spanning 4.5 hectares, the greenhouse houses a wide range of spaces: hotel rooms, restaurants, animal habitats and visitor routes. Behind this immersive experience lies a dense, demanding infrastructure that required no fewer than 620 kilometres of cables.

For Christophe Lahaye, Deputy Managing Director of the buildings and industry divisions at Eiffage Énergie Systèmes, Belux, the project stands out for several reasons: its scale, complexity and the mobilisation of the teams. “It is undoubtedly one of the most remarkable projects carried out by Collignon,” he says.

Behind the immersive experience Edenya offers visitors lies a dense, demanding infrastructure that required no fewer than 620 km of cables.

A comprehensive approach to the installations

Working from the design office’s plans, the teams carried out the detailed design and then installed the complete electrical systems. Work began once the glass roof was in place… and continued beyond the opening ceremony to incorporate the final requested changes.

All electrical packages were included: power and low-voltage systems, medium-voltage substations with standby generators, distribution boards, fibre-optic cabling and data networks. These were complemented by specialist installations such as room automation, access control, decorative lighting and evacuation sound systems.

Fire detection also presented a particular challenge. Conventional detectors could not be installed 25 metres up, so an aspirating system was implemented, with almost 4.6 kilometres of tubing able to analyse the air continuously, all in a humid environment.

At the height of activity, up to 70 to 75 people worked on site at the same time for more than six months, including subcontractors.

Some constraints stemmed from the equipment being installed: handcrafted light fittings, unusual materials and decorative features requiring bespoke fixing solutions. (photo: Pairi Daiza)

A project in constant motion

One of the main challenges was not just technical, but organisational. The project did not follow a linear progression, instead moving forward in line with work on the buildings and gardens, changes to the themes and coordination with other trades.

“We had to manage significant overlapping activities throughout, while remaining flexible enough to accommodate the client’s new requests,” explains Quentin Jacobs, Department Manager in the buildings division at Eiffage Énergie Systèmes, Belux.

There were numerous changes. The addition of two food outlets a month before handover required last-minute adjustments. Right up to the days before opening, the teams were still working on site, drilling through structures to route new cables.

In total, more than a hundred changes were made to the electrical panels after delivery, far exceeding usual practice. Some constraints were also linked to the equipment being installed: handcrafted light fittings, unusual materials and decorative features requiring bespoke fixing solutions.

All electrical packages were included, right down to the standby generators.

A collective success

Despite the constraints, pressure and constant adjustments, the project was carried out in a strong spirit of collaboration. Everyone involved shared a common goal: to deliver a project that was both technically demanding and unusual.

Ultimately, beyond the impressive figures, this project demonstrates above all the teams’ ability to adapt, innovate and work together in a complex environment. For many, it will remain a benchmark.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectConstruction
Share this article

Advertisement

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.