Impressive sawing and drilling work on the Sambre in Charleroi

Zabo réalise également des travaux de sciage et de forage à la fontaine située devant l’hôtel de ville de Charleroi.
Zabo réalise également des travaux de sciage et de forage à la fontaine située devant l’hôtel de ville de Charleroi.

For BAM Galère and Willemen Infra, Zabo carried out impressive sawing and drilling work along the banks of the Sambre near Charleroi station. The work forms part of a project to replace a 300 m-long quay wall with steps, revitalising the public space. “The cable sawing work on this project covered more than 2,000 m², which is quite exceptional,” explains Geert Vanderyse, director of Zabo NV.

As in Kortrijk and Ghent, the quay wall in Charleroi will be replaced with steps so that local residents and visitors can enjoy the Sambre. Geert Vanderyse explains: “The wall is 300 metres long, up to 2 metres thick and up to 7 metres high. If the demolition work had been carried out using conventional methods, it would have caused significant noise disturbance over a long period. The debris would also have ended up in the Sambre, which would have seriously disrupted navigation.”

For BAM Galère and Willemen Infra, Zabo carried out impressive sawing and drilling work along the banks of the Sambre near Charleroi station.

More than 2,000 m² to saw

By sawing the wall into blocks weighing 40 tonnes each, Zabo is applying its expertise and skills to minimise disruption. “The blocks are then lifted by crane and transported by water to a depot, where they will be processed,” explains Geert Vanderyse. “Sawing causes no noise disturbance, is more precise and much faster, and leaves no debris in the Sambre. In addition, all our machines are water-cooled, which means we can work dust-free. The cable sawing work covered 2,000 m², whereas we normally saw only 100 to 200 m² in an entire year. This was therefore a truly exceptional project.”

By sawing the wall into blocks weighing 40 tonnes each, Zabo is applying its expertise and skills to minimise disruption.

Drilling more than 400 holes 

Hundreds of holes also had to be drilled to enable the blocks to be lifted. Geert Vanderyse explains: “In total, we drilled more than 400 holes, with diameters ranging from 40 to 250 mm, in concrete slabs and walls up to 2.2 m thick. By sawing and drilling efficiently, we were able to complete the preparatory work for the main contractor to perfection. And we did it all using our own equipment, from cable saws to drills and wall saws. We were able to complete the work to the agreed schedule, thanks in particular to the excellent cooperation with BAM Galère and Willemen Infra.”

To enable the blocks to be lifted, holes are drilled in each one.

A bespoke project

In addition to the major works at Charleroi station, Zabo is also carrying out drilling and sawing work at the fountain in front of the town hall in the Hainaut capital. “We’re doing this for BAM Galère, which recently became part of Groupe Thomas & Piron. At the same time, we shot-blasted the tunnel roof panels there for Viabuild. These are all projects tailored to Zabo. We know the techniques, have more than 40 years of experience to draw on and, above all, can handle the volume of work, both in terms of manpower and equipment,” concludes Geert Vanderyse.   

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeTransforming infrastructure and territories
  • SubjectConcrete
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.