Charter on the delivery and placing of ready-mixed concrete (RMC)

With around 12 million cubic metres placed every year, ready-mixed concrete (RMC) is by far the most important construction material.
Against this backdrop, the Federation of General Contractors in Construction (FEGC) and the Federation of Ready-Mixed Concrete (FEDBETON) have approved a Charter setting out recommendations and guidelines, with a focus on dialogue between supplier and user.
Safety
The Charter first sets out a list of safety instructions to be followed on construction sites, including wearing personal protective equipment and using outrigger pads when pumping, since mixer trucks and concrete pumps are heavy construction machinery. It also stresses that the contractor must arrange suitable signage and permits when occupying the road or public space is necessary.
Mixer trucks and concrete pumps must, of course, comply with legal requirements and undergo regular technical inspections. As deliveries may take place near high-voltage power lines, the contractor must flag this when ordering the concrete.
The Charter also states that emptying the concrete skip (cufa) into the mixer truck is prohibited, as handling the cufa is a hazardous operation that must be carried out under optimal safety conditions.
Quality
When it comes to quality, the clear choice is BENOR-certified concrete, as it guarantees compliance with the standards in force. The contractor must also ensure that the concrete ordered is suitable for the intended application and the placing techniques to be used. The concrete supplier guarantees the specified workability for 30 minutes after the concrete arrives on site, in accordance with the BENOR application regulations.
“Good communication is vital in this context,” confirms Marc Jonckheere, President of FEDBETON. “If the contractor orders concrete that is suitable for the application and has the right level of workability, many problems can be avoided. The workability of RMC can be increased by up to one consistency class by adding admixtures, a task carried out by the mixer truck driver. Adding water is prohibited and results in the loss of the BENOR mark.”
Communication and planning
Mr Jonckheere continues: “The most important thing is to communicate, and above all, to do so in good time. Communication at the ordering stage helps ensure efficient delivery. A coordination meeting beforehand is also very useful for large deliveries. Building a traditional house generally presents no problems, but as construction becomes larger and more complex, a lack of planning and coordination can cause serious problems.”
“It is important for all the parties involved to agree on the delivery arrangements. With this in mind, every driver receives five days of training to ensure they are fully familiar with all the key aspects of concrete placement,” explains the President of FEDBETON.
Environment
The Charter’s final point concerns the environment, in particular the ambition to reduce the ecological footprint. This applies not only to transport but also to ordering concrete. It is important to order the right quantity of concrete to limit surplus, which by definition must be recycled.
“We will do our best to circulate the Charter as widely as possible as an advisory document, through the press and media. We hope it will help improve communication between all the parties involved and have many positive effects,” concludes Marc Jonckheere.