Underground infrastructure and sewerage
Renovating an underground structure with limited access
Texte Philippe Selke Photos Nelles

In Spa, work has begun to renovate the vaulted culverts carrying the Wayai beneath the town, following a preparatory phase and a series of condition surveys. Parts of the vaults had been weakened by rising water during the July 2021 floods, leading to a localised collapse. Nelles has been commissioned to carry out reinforcement works over approximately 125 metres. Although the company has extensive experience in watercourse maintenance, this is its first renovation project in an underground environment with limited access.
In the spa town, the local river has flowed underground since the 19th century. The work now under way, scheduled to last 200 working days, is not intended to uncover the river, but rather to secure the Wayai’s underground course. Raphaël David, Site Manager at Nelles, explains: « Our staff enter beneath the vaults through a secure access point in ruelle Hanse (editor’s note: where the vaults collapsed in 2023), but we also have an essential supply area at Place royale, with an 80 cm hatch that will be used, among other things, to bring in materials. »


Reinforcement by shotcreting
Raphaël David continues: « Water caused the foot of the vault to subside and the (double) vault to deform at several points. It took a long time to get the renovation project under way, with an in-depth study carried out by a consultancy appointed by the administration and a final tender submitted in July 2025. »
The work will proceed as follows: stabilising and securing the subsided areas, demolishing and rebuilding the vault feet in three-metre sections, installing reinforcement on the existing vault, then applying reinforced concrete by shotcreting across the entire interior surface of the vaults to create a robust protective shell.

Safety is non-negotiable
Since its beginnings, Nelles has developed its expertise in « everything beneath our feet ». With this first-of-its-kind project, the Malmedy-based company is breaking new ground, while taking every measure to avoid being thrown in at the deep end. The work is taking place in an underground environment with an internal height of approximately two metres. Lionel Lejeune, Level 1 Prevention Adviser at Nelles, explains: « Particular attention is being paid to work organisation and staff safety. A safety coordinator has been appointed, with close cooperation between the site teams and prevention specialists. Specific measures are in place: daily safety briefings, checklists, constant communication between the inside and outside, suitable lighting… Atmospheric checks are carried out as a precaution during work. »
Fortunately, the presence of two parallel vaults along the section being renovated means water can be diverted to one side while work is carried out on the other. Weather monitoring is nevertheless essential: forecasts from the Royal Meteorological Institute of Belgium (IRM) are tracked to anticipate work stoppages in the event of prolonged heavy rain. Work is halted if the water flow rises above a threshold set in consultation with the authorities, to ensure staff safety.
Specific training in confined-space rescue has also been organised, including both theory and practical exercises. Finally, access to the site is restricted and managed to ensure rapid evacuation in an emergency, with permanent access reserved for the emergency services.
While Nelles’s roadworks teams are working on the redevelopment of the route through Spa, a team of five suitably trained skilled workers is heading underground to restore the Wayai to its peaceful course.

Een zakelijke vraag aan NELLES frères SA? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeRenovating existing buildings
- SubjectUnderground infrastructure and sewerage
- CompanyNELLES frères SA