Along the E40 in Remicourt, a major construction project is moving at high speed: a new rest area with 129 spaces for lorry drivers, offering maximum security and comfort. The first of its kind in Belgium and partly funded by European funds, this fully equipped parking facility is due for completion by 30 June. Replacing the conventional drainage system originally planned with two rows of TUBAO galvanised steel pipes is helping the project progress quickly. The alternative was successfully proposed by contractor Lucas David in close collaboration with Deschacht.
Dimitri Steilen, head of Deschacht’s Wallonia design office, and Gaëtan Lemestré, technical director at public and private works contractor Lucas David (Oreye), have known and appreciated each other for 10 years. Lemestré even installed the first-ever TUBAO in Wallonia back then! Versatile, these corrugated galvanised steel tanks provide an effective solution for retaining, diverting, infiltrating or storing rainwater. TUBAO supplies corrugated pipes in a range of sizes, lengths and thicknesses. In Remicourt, it was not 1 but 14 pipes, each 21 m long, that were installed in two trenches… in just a day and a half! The aim is to equip the parking facility with a stormwater basin that will retain rainwater before it is discharged into the public network.

A 1,200 m3 stormwater basin made up of 300 m of TUBAO, installed in 2 days!
Gaëtan Lemestré explains: “Each pipe is 21 metres long, the maximum permitted to avoid the need for an abnormal load, and weighs between 2 and 3 tonnes. Their light weight makes them easy to handle with a standard crane. We were therefore able to install 14 of these units in less than 2 days. They were then connected with coupling bands to form two long parallel lines alongside high-capacity slot drains, which will connect directly to them. All that remains is to seal the joints and backfill.”
This means no kilometres of pipework or concrete inspection chambers, as required by a conventional drainage system. The galvanised steel pipes have a diameter of 2.2 metres and can be inspected and maintained very easily through manholes.


A winning alternative
Dimitri Steilen: “Our design team worked with Lucas David and together we completely reviewed and optimised the drainage network, while strictly adhering to the specifications and applicable standards. This alternative helped us stand out and win the contract. The architect responsible for the project on behalf of the client was convinced by the benefits our proposal offered, both for the successful delivery of the construction work itself and for future operation. The experience Deschacht and Lucas David have built up with this type of product once again made all the difference.”

A welcome break
The project can now continue without delay with the partner companies, with completion scheduled for the end of June: construction of the parking facility’s sub-base and foundations, followed by the installation of the asphalt surfacing; construction of a building with 10 rooms, a dining room and sanitary facilities; and finally, construction of a roundabout to improve traffic flow in the surrounding area.
Close to the E40, E42, E313 and E25 motorways, as well as Bierset Airport, this unique secure parking facility is ideally located. There is little doubt that the owner of HesbyMazout, who initiated the project, was right: it meets an urgent need. Lorry drivers travelling across Europe will feel a little more at home here, whatever the weather.
Een zakelijke vraag aan DESCHACHT Plastics? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectUnderground infrastructure and sewerage
- CompanyDESCHACHT Plastics