Underground infrastructure and sewerage
Construction site management paving the way for new mobility
Texte Philippe Selke Photos Cvisuels

A major long-term project got under way in Spa in early April: the complete reconstruction of the section of the RN62 running right through the town, including the installation of utility services, partial renewal of the sewer network, complete rehabilitation of the road and various associated improvement works planned by the City of Spa. This project, named “La Traversée de Spa”, is expected to take around 3 years, with careful phasing designed to keep traffic and local businesses running. Roadworks contractor Nelles has been appointed to take on this major challenge. Jean Nelles, director and site manager, outlines the project’s key features.

A wide range of works for a diverse client base
Demolition, installation of utility services, sewer works, construction of parking spaces, pavements and a cycle lane, rehabilitation of roads and roundabouts, … these are just some of the areas in which the Malmedy-based company excels, carrying out the work with its own teams (currently around 20 people are on site). In addition, some works require specialist expertise, such as pipe relining, paving and asphalting. Jean Nelles: “The Spa crossing brings together all our areas of expertise on a single site. The main challenge is managing the schedule and mobility.”
Nelles meets weekly with no fewer than 7 clients: SPW MI, AIDE, Spadel, SWDE, RESA, Unifiber and the City of Spa, to ensure their respective requirements are fully coordinated. Jean Nelles: “When working on underground networks, you have to deal with unforeseen issues and find solutions quickly to avoid bringing the project to a halt.”

Phasing is essential
Jean Nelles: “To maintain a certain level of mobility in the town during the three years the works will take, we have to phase the project.” This major project has therefore been divided into 9 phases, 3 of which are currently under way in parallel: construction of a park-and-ride car park by the station, road resurfacing works on Avenue Reine Astrid, and the installation of gas pipes for RESA and fibre-optic cable for Unifiber on Rue de la Sauvenière. He explains: “The Unifiber works take priority because they must be completed by 31 August. We will then move on to the other utility services, followed by the improvements for SPW-MI and the City of Spa. Where possible, we keep one lane open to traffic, sometimes using temporary traffic lights to manage alternating flows, but more often by setting up local diversions. Full closures of the RN62 are currently limited to milling and asphalting works.”

Enhancing the town and its surroundings
Nelles is currently setting up a temporary recycling centre near the site, allowing it to recover demolition materials locally, including concrete, crushed stone and soil, for reuse on site in the road foundations. However, these recycled materials cannot be used near the Spa Monopole water catchment areas, where schist and sandstone products from the company’s quarries at Warche in Bévercé-Malmedy will be required..
Coordination between all the clients, as well as between Nelles’ own specialist teams (utility services, roadworks and sewer works), is not only essential to the smooth running of the project, but also a key factor in keeping local residents and businesses satisfied throughout this major undertaking. Jean Nelles adds: “Spa has two busy periods every year: summer, with the 24 heures, Formula 1 and the Francofolies, and winter, with the year-end festivities. Work is then paused, and the town is handed back to its residents and visitors.”
Een zakelijke vraag aan NELLES frères SA? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeTransforming infrastructure and territories
- SubjectUnderground infrastructure and sewerage
- CompanyNELLES frères SA