While the Liège Tram works are highly visible above ground, a great deal is also happening beneath the feet of the people of the Cité ardente. Hundreds of kilometres of cables are being laid to supply the infrastructure with electricity. At regular intervals, they pass through access chambers for future inspection. Superplastic tells us about the product it selected as a local supplier, to meet the client’s needs.

The Rom-Box from German manufacturer Romold is the ideal alternative to concrete draw pits. It combines the stability (class D400) and standard dimensions of concrete systems with the flexibility and quick, easy installation of plastic systems. The Rom-Box can be used as a draw pit or cable distribution chamber. Its low weight makes it easy to install. It is modular and available in various sizes.

A draw pit is first used to pull cables through and distribute electricity to different areas. Applications are numerous, whether supplying lighting columns, barriers or traffic lights, or controlling an irrigation system, … These pits also provide access to cables for inspection, making it possible to quickly identify the section that may be causing a problem.

“The pit selected, like its cover, depends on the nature of the ground, the internal space required, the load it must bear, …”

Xavier Cornet, Key Account Manager at Superplastic: “We offer various polypropylene and polyethylene models. The model selected for the Tram is the Rom-Box 57 115 86 B/D, 86 cm high and weighing 187 kilos. The pit selected, like its cover, depends on the nature of the ground, the internal space required, the load it must bear, … all of this can be tailored to the client’s requirements.”

In ground exposed to moisture, the watertightness of the pit and its connections is crucial. Jean de Brouwer, Sales Director at Superplastic: “We are currently carrying out a project where the draw pit must be completely watertight. This is a very specific case: we are making branch connections at precise locations and welding the end fittings onto the pit so that the ducts can be connected with 100% watertightness.” Cable ducts are, of course, also available from Superplastic’s extensive range.  

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectUnderground infrastructure and sewerage
Share this article

Follow on Construire la Wallonie

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.